Parameter assignment of a Mobile Client
4.6 General settings
Mobile Client900RXA
70
Operating Instructions, 07/2015, A5E36360099-AA
4.6.6.2
Setting the project storage location and start delay
There are various storage locations available for storing the compressed source file of your
project, for example, the external memory card or a network drive. This section describes
how to set the location and configure the delay time for the project start.
Requirement
You have opened the "Directories" tab in the "Transfer Settings" dialog with the "Transfer"
icon.
①
Storage location for project file, cannot be set
②
Directory where the compressed source file of your project is saved
③
Storage location and initialization file for process operation, cannot be set
④
Delay time for project start
Procedure
1.
Select a memory location from the "Project Backup" text box.
The storage location can be a storage medium or the local network. During the next
backup process, the project's source file is stored in the specified location.
2.
Select the desired delay time for project start from the "Wait [sec]" selection box.
The delay time sets how long the Start Center is displayed before the project starts.
Permissible values are 1, 3, 5 and 10 seconds.
–
0 seconds
The project starts immediately. The Start Center is not displayed.
–
Forever
The project is not started. The Start Center is displayed permanently.
Note
For the Start Center to be accessed after the project starts, an operating element must be
configured in the project with the "Close project" function.
3.
Confirm your entries.
The dialog closes.
The storage location and delay time for the HMI device are now set.