Starting Up
6-4
S7-400 and M7-400 Programmable Controllers Hardware and Installation
A5E00069481-04
Table 6-1
Checklist to be Used Before Switching On for the First Time, continued
Module Settings
Is the CPU mode switch set to
STOP?
1
Are the numbers of the racks cor-
rectly set on the coding switches of
the receive IMs and not duplicated?
7
If measuring range modules are fitted
on the analog input modules, are they
correctly set?
5, 6
Have the rules for connection been
observed?
Have the correct cables been used
for connections to existing ERs?
7
Is the last receive IM of each connec-
tion chain terminated with the right
terminator?
7
Power Supply Module
Is the power supply connector cor-
rectly wired?
On AC PS modules, is the voltage
selector switch set to the available
line voltage?
3
On fan subassemblies, is the voltage
selector switch set to the available
line voltage?
9
Are all power supply modules swit-
ched off (Standby switch set to )?
3
Is the BATT INDIC switch for battery
monitoring correctly set
(see Table 6-2)?
3
Has the connection to the supply
been made?
Line Voltage
Is the available line voltage correct?
3
According to the backup concept, Table 6-2 shows how you must set the battery
monitoring switch on the different power supply modules.