MOBILETT Plus / - E/ - M
SPR8-215.898.01
Page 8 of 28
Siemens-Elema AB
Rev. 05
01.02
SPS-UD
Solna, Sweden
10 - 8
Mechanical systems
•
Raise the single tank to maximum height and secure it with a ceiling support (Fig. 10).
•
Remove the tilt bar (Fig. 11).
•
Remove the supporting wheels behind the tilt bar.
•
Put the protective mat under the unit to protect the floor from damage.
MOBILETT Plus and Plus M only
•
Disconnect all cables, ground connections and K68, according to (Fig. 12).
•
Remove the locking rings.
•
Remove the bearing rings.
•
Remove the shaft.
•
Let the turn plate down and remove it.
The ceiling suspension must be able to hold a weight of 100 kg,
since the entire weight of the arm will be on the ceiling support
once the spring is removed.
If not, the arm and single tank will fall.
Make sure the ceiling support is sufficient.
Do not stand under the single tank or the arm system during the
work that follows.
Fig. 12
CAUTION
NOTE
K68
Shaft