18
MSA400 smart
Installation and operating instructions
05.2017
8. Commissioning
8.1 General information for commissioning
• Following installation of the MSA400 smart (initial commissioning), you must carry out a reference run as well as a
calibration and teach-in run.
• The reference run, as well as the calibration and teach-in run help to determine the size of the slide element and the
displacement force.
• The reference run must be performed again in the event of a power failure. The calibration and teach-in run only has to be
performed when commissioning the equipment.
• Any tasks relating to commissioning may only be completed by qualified professionals.
8.2 Reference run
1. The sliding sash must be in the CLOSED position in order to begin the reference run. If necessary, slide the sash to this
position manually.
2. Supply power to the MSA400 smart system.
3. Press the operating push button. The reference run starts. During the reference run, the sash is unlocked and then locked
again.
4. Wait approx. 4 - 10 seconds until the sash is locked. The LED switches off once the reference run is complete.
1.
2.
3.
4.
4 - 10 Sek.
Note:
A reference run must also be performed after a power failure in order to re-initialise the MSA400 smart system.