background image

 |   

INTERNATIONAL

QUICK GUIDE

Step 1

SAFETY

Read & understand the safety section.

Step 7

SECURE DROPPER & 

TRANSITION

Use the TEK screws provided. Break the 

transport clips for the AutoWinterseal.

Step 14

INSTALL INLET SOLENOID

Use the supplied hose set and fittings. 

Note the water flow direction marking on 

the solenoid.

Step 20

SET THE WATER LEVEL

Turn on the mains water and adjust the 

float to allow water to fill to the required 

level.

Step 21

COMMISSIONING THE COOLER

Switch the mains power on and test run 

the cooler.

Step 2

COOLER LOCATION

Check cooler location. Consider 

regulations. Discuss with customer.

Step 8

CHECK AutoWinterseal™

Check operation of the AutoWinterseal. 

Ensure AutoWinterseal moves freely.

Step 15

INSTALL DRAIN VALVE

Never drain waste water directly onto the 

roof. Be sure to use supplied ‘O’ Rings 

and fittings.

Step 3

REMOVE VENTURI

Press the clip or remove the screws on 

both sides of the venturi to release.

Step 9

CONVEY COOLER TO ROOF

Page 1

Page 8

Page 9

Page 4

Page 6

Page 10

Page 13

Page 6

Page 14

Page 4

Always use 2 persons to position the 

cooler when handling manually.

Step 19

MOUNT AND CONNECT THE 

CONTROLLER

Page 12

CPQ/LCQ/LCS

BMQ

LCQI

Step 13

INSTALL FLOAT VALVE

Assemble the float valve to the cooler. 

Ensure all washers and o-rings are in 

place. No thread tape is required. 

Page 9

Summary of Contents for BMQ

Page 1: ...INSTALLATION MANUAL LCQ LCS LCQI BMQ CPQ TBS TBQI TBSI TBQ Evaporative Cooler Original English Instructions Original English Instructions ...

Page 2: ...AN ASSEMBLY 11 ELECTRICAL CONNECTION 11 CONNECTING THE WATER PUMP 12 CONNECTING THE MAGIQTOUCH MAGIQCOOL CONTROLLER 12 MAGIQTOUCH CONTROLLER DISPLAY INFORMATION 13 CHANGING THE WATER MANAGEMENT METHOD FOR THE MAGIQCOOL CONTROL 13 CHANGING THE SALINITY CONTROL METHOD FOR THE MAGIQCOOL CONTROL 13 SETTING THE WATER LEVEL 13 FAULT CODES INDICATED BY LED s ON THE COOLER ELECTRONICS MODULE 14 COMMISSION...

Page 3: ...s it is just is a matter of looking at the job to be done and considering what action s are necessary so the person doing the job does not injure themselves This should be considered in terms of What are the chances of an incident happening What could the possible consequence be What can you do to reduce or better still completely eliminate the risk Some points to consider What is the best and saf...

Page 4: ...cation Consider regulations Discuss with customer Step 8 CHECK AutoWinterseal Check operation of the AutoWinterseal Ensure AutoWinterseal moves freely Step 15 INSTALL DRAIN VALVE Never drain waste water directly onto the roof Be sure to use supplied O Rings and fittings Step 3 REMOVE VENTURI Press the clip or remove the screws on both sides of the venturi to release Step 9 CONVEY COOLER TO ROOF Pa...

Page 5: ...sition Step 5 PREPARE THE DROPPER Cut hole fit the grommet in the dropper for power and control cables Step 11 CABLE INSTALLATION Run the power and control cable down the conduit and out through the grommet Step 17 INSTALL VENTURI FAN Ensure the venturi is fully located into the tank and the motor lead is not caught or pinched Step 6 MOUNT DROPPER Position level and secure the dropper Flash the dr...

Page 6: ...ust be mounted at least 3m 10 preferably 5m 17 away from any TV antenna or antenna cables Make sure the cooler is not between the antenna and the transmission tower that is providing the television signal to the home Allow adequate access to and around the cooler for maintenance Provision must be made for access to electricity water supplies and drains Note Do you need to discuss the installation ...

Page 7: ...dropper is suitable and is secured adequately for wind conditions at the site Additional restraints may be required if the cooler is more than 200mm 8 higher than the roof timbers or design wind velocity at the site exceeds 43m s 141fps In exposed or very high wind areas use 16 screws minimum shank diameter 5 2mm 7 32 to secure the dropper In areas subject to hurricanes windstorms or where the coo...

Page 8: ...tach ropes or slings through the central tank hole Do not slide the cooler lift and carry it Do not drop the cooler Always handle the cooler with care AutoWinterseal CONVEYING THE COOLER TO THE ROOF Caution Do not take risks when raising the cooler to the roof for installation Use safety equipment appropriate procedures and always have assistance It is recommended that at least 2 people move the c...

Page 9: ...lot in the transition control cable first and then seal the hole with the plug provided Important Test the AutoWinterseal operation and ensure that the cables in the dropper do not interfere with the operation of the assembly ILL1288 C ILL1181 A CABLE INSTALLATION cont CABLE INSTALLATION For Rest of the World Pass the taped end of the wall control cable through the conduit adaptor factory fitted i...

Page 10: ... required Water Connection BSP Min Water Pressure 100kPa 15psi Max Water Pressure 800kPa 115psi Min Water Flow 8 liters min 2 1 gallons min Max Water Temperature 40 C 104 F Important If the water pressure exceeds maximum specification then a pressure reducing valve is required and must be supplied and fitted by the installer A permanent water supply is required to be connected to the cooler The wa...

Page 11: ...d valve then push the other end through the hole in the transition as shown Pull the cable through from inside the cooler and route the cable as shown This will be connected later INSTALLING THE INLET SOLENOID INSTALLING THE FLOAT VALVE Assemble the float valve to the cooler as shown Ensure all washers and O rings are in place No thread tape is required Do not over tighten the plastic fittings Mak...

Page 12: ...EED FUNNEL Assemble the bleed funnel as shown Make sure the bleed funnel is correctly oriented and that the o rings are fitted before placing it into the hole Screw the nut up tightly by hand underneath the cooler Make sure that you use the correct drain adaptor Drain water from the bleed funnel must be carried away to a suitable discharge point on the building or property in accordance with local...

Page 13: ...e sits Snare the lead into one of the brackets at the top of the opening E Ensure the bottom of the lead is aligned with the bracket inside the tank Failure to do this may result in the cable being caught between the outside of the bracket and the venturi A If fitted route the motor tether through bracket at A and wedge it between the venturi and the tank at edge B ELECTRICAL CONNECTION Connect th...

Page 14: ...trol cable Longer cable lengths are available from Seeley Important The maximum cable length allowed from the MagIQtouch Controller to the first cooler is 25m 82 For any additional coolers added into the system with a link module the maximum allowed length is 40m 131 Therefore failure of the product or components to operate correctly due to modification to supplied cables or the use of non approve...

Page 15: ...down for at least 3 seconds and then press while still pressing The setting A1 will be displayed release both buttons and then press A number will now be displayed Press or until the number displayed corresponds to the desired setting 0 Salinity Control 1 Timed Drain every 65 mins Press to complete the adjustment Exit the programming mode by pressing To enter Parameter mode the following process m...

Page 16: ...G THE WATER LEVEL cont If the level is too high rotate the float clockwise Drain some water from the tank and allow it to refill to the new set point If too low rotate the float in an anti clockwise direction The correct water level is approximately 5mm below the surface of the tank the float valve is mounted on It is advisable to check the water level again after the float valve washer has bedded...

Page 17: ... to the cooler was made NO EXTERNAL LEAKS The water is connected with no leaks at fittings NO INTERNAL LEAKS Check the internal water hose is securely fitted to water distribution spreader on the lid and to the pump SECURE Water pipes are correctly saddled as per plumbing regulations OWNER INSTRUCTIONS The owner has been instructed on how to isolate the water to the system in case of emergency DRA...

Page 18: ...TINGS COMMISSIONING COMPLETION CHECKLIST cont POWER REGULATIONS The power supply adheres to all local and national regulations and is wired back to the distribution board on its own separate circuit CHECK CABLES Cables have been correctly connected to the control boxes Power supply Motor cable s Control cable Drain valve Solenoid cable Pump cable Probe cable OWNER INSTRUCTIONS The owner has been i...

Page 19: ...fault condition via the tri colour LED on cooler electronics module Rectify fault as indicated and restart the cooler Controller failure Replace controller Pump runs but no water circulation or Pump runs but pads lack water Insufficient water in tank Adjust float level Water hoses blocked Check and clean out blockage Pump strainer blocked Clean pump strainer Insufficient water supply pressure Chec...

Page 20: ... Please contact your local distributor seeleyinternational com MANUFACTURED BY SEELEY INTERNATIONAL PTY LTD 112 O SULLIVAN BEACH RD LONSDALE SA 5160 AUSTRALIA IMPORTED BY SEELEY INTERNATIONAL EUROPE LTD UNIT 11 BYRON BUSINESS CENTRE DUKE STREET HUCKNALL NOTTINGHAM NG15 7HP UNITED KINGDOM SEELEY INTERNATIONAL AMERICAS LTD 1202 NORTH 54TH AVENUE BUILDING 2 SUITE 117 PHOENIX ARIZONA 85043 USA SEELEY ...

Reviews: