background image

 |   

INTERNATIONAL

CPQ/LCQ/LCS

TBQ/TBS

BMQ

LCQI/TBQI/TBSI

COOLER LOCATION

Check proposed cooler location to ensure it is structurally 

capable of supporting the weight of the cooler. If the roof is 

structurally inadequate, provide an alternate load bearing 

structure.
The ideal location for the cooler is in a central position on the 

roof (away from sleeping areas and where people spend most 

of their time) so that the duct runs are of approximately the 

same length. Carefully consider neighbouring residences and 

noise levels when locating the cooler, if necessary talk to the 

customer and the neighbour before carrying out the installation.
Always locate the cooler where it will receive adequate fresh air 

and not in a recess where it may be starved for air or where the 

air is polluted. 

Ensure location is a minimum of: 

• 

3m (10’) from a solid fuel heater flue, 

• 

1.5m (5’) from a gas flue, 

• 

5m (17’) from a sewer vent, and 

• 

600mm (2’) from a wall.

ILL1150-B

ILL2111-B

ILL1155-C

REMOVING THE VENTURI

Once the pad frames have been removed, detach the  

venturi / fan assembly and the electronics module.
For LCQ/LCS/TBQ/TBS & CPQ models, disengage the two 

venturi clips as shown. For LCQI/TBQI/TBSI & BMQ models, 

remove the 2 screws securing the venturi to the tank.

X

ILL1150-B

REMOVING THE TRANSITION

• 

The cooler must be mounted at least 3m (10’), preferably 

5m (17’), away from any TV antenna or antenna cables. 

Make sure the cooler is not between the antenna and the 

transmission tower that is providing the television signal to the 

home.

Allow adequate access to and around the cooler for 

maintenance. Provision must be made for access to electricity, 

water supplies and drains.

Note!

 Do you need to discuss the installation of items like 

safety anchor points with the customer?

Disconnect the electronics module from the tank by removing 

the screw under the switch. The isolation switch cannot be 

activated with this screw removed. Remove the pump and motor 

cables from the plugs in the electronics module.

Note!

 Place the electronics module and the screw safely to 

one side for later use. Do not re-fit the electronics module, as 

the motor plug will require connection to the underside of the 

module when the venturi is refitted into the cooler. 

Lift the venturi and fan assembly out of the cooler, taking care of 

the motor lead(s).

The venturi and fan assembly can be placed on to the ground 

until the rest of the cooler has been installed on the dropper.

Turn the cooler onto its side to remove the transition.  

There are clips in each of the four corners that will disengage 

once the transition is given a firm pull.
If any of the corners are difficult to remove, do not use 

excessive force. Gently squeeze the clips together and remove 

the transition one corner at a time.

ILL1053-C

REMOVING THE VENTURI 

cont

Summary of Contents for BMQ

Page 1: ...INSTALLATION MANUAL LCQ LCS LCQI BMQ CPQ TBS TBQI TBSI TBQ Evaporative Cooler Original English Instructions Original English Instructions ...

Page 2: ...AN ASSEMBLY 11 ELECTRICAL CONNECTION 11 CONNECTING THE WATER PUMP 12 CONNECTING THE MAGIQTOUCH MAGIQCOOL CONTROLLER 12 MAGIQTOUCH CONTROLLER DISPLAY INFORMATION 13 CHANGING THE WATER MANAGEMENT METHOD FOR THE MAGIQCOOL CONTROL 13 CHANGING THE SALINITY CONTROL METHOD FOR THE MAGIQCOOL CONTROL 13 SETTING THE WATER LEVEL 13 FAULT CODES INDICATED BY LED s ON THE COOLER ELECTRONICS MODULE 14 COMMISSION...

Page 3: ...s it is just is a matter of looking at the job to be done and considering what action s are necessary so the person doing the job does not injure themselves This should be considered in terms of What are the chances of an incident happening What could the possible consequence be What can you do to reduce or better still completely eliminate the risk Some points to consider What is the best and saf...

Page 4: ...cation Consider regulations Discuss with customer Step 8 CHECK AutoWinterseal Check operation of the AutoWinterseal Ensure AutoWinterseal moves freely Step 15 INSTALL DRAIN VALVE Never drain waste water directly onto the roof Be sure to use supplied O Rings and fittings Step 3 REMOVE VENTURI Press the clip or remove the screws on both sides of the venturi to release Step 9 CONVEY COOLER TO ROOF Pa...

Page 5: ...sition Step 5 PREPARE THE DROPPER Cut hole fit the grommet in the dropper for power and control cables Step 11 CABLE INSTALLATION Run the power and control cable down the conduit and out through the grommet Step 17 INSTALL VENTURI FAN Ensure the venturi is fully located into the tank and the motor lead is not caught or pinched Step 6 MOUNT DROPPER Position level and secure the dropper Flash the dr...

Page 6: ...ust be mounted at least 3m 10 preferably 5m 17 away from any TV antenna or antenna cables Make sure the cooler is not between the antenna and the transmission tower that is providing the television signal to the home Allow adequate access to and around the cooler for maintenance Provision must be made for access to electricity water supplies and drains Note Do you need to discuss the installation ...

Page 7: ...dropper is suitable and is secured adequately for wind conditions at the site Additional restraints may be required if the cooler is more than 200mm 8 higher than the roof timbers or design wind velocity at the site exceeds 43m s 141fps In exposed or very high wind areas use 16 screws minimum shank diameter 5 2mm 7 32 to secure the dropper In areas subject to hurricanes windstorms or where the coo...

Page 8: ...tach ropes or slings through the central tank hole Do not slide the cooler lift and carry it Do not drop the cooler Always handle the cooler with care AutoWinterseal CONVEYING THE COOLER TO THE ROOF Caution Do not take risks when raising the cooler to the roof for installation Use safety equipment appropriate procedures and always have assistance It is recommended that at least 2 people move the c...

Page 9: ...lot in the transition control cable first and then seal the hole with the plug provided Important Test the AutoWinterseal operation and ensure that the cables in the dropper do not interfere with the operation of the assembly ILL1288 C ILL1181 A CABLE INSTALLATION cont CABLE INSTALLATION For Rest of the World Pass the taped end of the wall control cable through the conduit adaptor factory fitted i...

Page 10: ... required Water Connection BSP Min Water Pressure 100kPa 15psi Max Water Pressure 800kPa 115psi Min Water Flow 8 liters min 2 1 gallons min Max Water Temperature 40 C 104 F Important If the water pressure exceeds maximum specification then a pressure reducing valve is required and must be supplied and fitted by the installer A permanent water supply is required to be connected to the cooler The wa...

Page 11: ...d valve then push the other end through the hole in the transition as shown Pull the cable through from inside the cooler and route the cable as shown This will be connected later INSTALLING THE INLET SOLENOID INSTALLING THE FLOAT VALVE Assemble the float valve to the cooler as shown Ensure all washers and O rings are in place No thread tape is required Do not over tighten the plastic fittings Mak...

Page 12: ...EED FUNNEL Assemble the bleed funnel as shown Make sure the bleed funnel is correctly oriented and that the o rings are fitted before placing it into the hole Screw the nut up tightly by hand underneath the cooler Make sure that you use the correct drain adaptor Drain water from the bleed funnel must be carried away to a suitable discharge point on the building or property in accordance with local...

Page 13: ...e sits Snare the lead into one of the brackets at the top of the opening E Ensure the bottom of the lead is aligned with the bracket inside the tank Failure to do this may result in the cable being caught between the outside of the bracket and the venturi A If fitted route the motor tether through bracket at A and wedge it between the venturi and the tank at edge B ELECTRICAL CONNECTION Connect th...

Page 14: ...trol cable Longer cable lengths are available from Seeley Important The maximum cable length allowed from the MagIQtouch Controller to the first cooler is 25m 82 For any additional coolers added into the system with a link module the maximum allowed length is 40m 131 Therefore failure of the product or components to operate correctly due to modification to supplied cables or the use of non approve...

Page 15: ...down for at least 3 seconds and then press while still pressing The setting A1 will be displayed release both buttons and then press A number will now be displayed Press or until the number displayed corresponds to the desired setting 0 Salinity Control 1 Timed Drain every 65 mins Press to complete the adjustment Exit the programming mode by pressing To enter Parameter mode the following process m...

Page 16: ...G THE WATER LEVEL cont If the level is too high rotate the float clockwise Drain some water from the tank and allow it to refill to the new set point If too low rotate the float in an anti clockwise direction The correct water level is approximately 5mm below the surface of the tank the float valve is mounted on It is advisable to check the water level again after the float valve washer has bedded...

Page 17: ... to the cooler was made NO EXTERNAL LEAKS The water is connected with no leaks at fittings NO INTERNAL LEAKS Check the internal water hose is securely fitted to water distribution spreader on the lid and to the pump SECURE Water pipes are correctly saddled as per plumbing regulations OWNER INSTRUCTIONS The owner has been instructed on how to isolate the water to the system in case of emergency DRA...

Page 18: ...TINGS COMMISSIONING COMPLETION CHECKLIST cont POWER REGULATIONS The power supply adheres to all local and national regulations and is wired back to the distribution board on its own separate circuit CHECK CABLES Cables have been correctly connected to the control boxes Power supply Motor cable s Control cable Drain valve Solenoid cable Pump cable Probe cable OWNER INSTRUCTIONS The owner has been i...

Page 19: ...fault condition via the tri colour LED on cooler electronics module Rectify fault as indicated and restart the cooler Controller failure Replace controller Pump runs but no water circulation or Pump runs but pads lack water Insufficient water in tank Adjust float level Water hoses blocked Check and clean out blockage Pump strainer blocked Clean pump strainer Insufficient water supply pressure Chec...

Page 20: ... Please contact your local distributor seeleyinternational com MANUFACTURED BY SEELEY INTERNATIONAL PTY LTD 112 O SULLIVAN BEACH RD LONSDALE SA 5160 AUSTRALIA IMPORTED BY SEELEY INTERNATIONAL EUROPE LTD UNIT 11 BYRON BUSINESS CENTRE DUKE STREET HUCKNALL NOTTINGHAM NG15 7HP UNITED KINGDOM SEELEY INTERNATIONAL AMERICAS LTD 1202 NORTH 54TH AVENUE BUILDING 2 SUITE 117 PHOENIX ARIZONA 85043 USA SEELEY ...