![SEA STK3-GMV10 Manual For Installation And Use Download Page 15](http://html.mh-extra.com/html/sea/stk3-gmv10/stk3-gmv10_manual-for-installation-and-use_1220677015.webp)
SEA SYSTEMS
INSTALLATION AND USE
STK3-GMV10 Control panel and Pre-wiring
For Hydraulic Elevators
MSTK3-GB
Rev.04
05/02/12
© Sea Systems S.r.l.
Page 15 of 81
B.7.2. S
HUNT
C
ONNECTIONS TO THE SHAFT LINE
The shunt connections to the line (see the installation schematic diagram) must be performed
using the red connectors for 0,75 mm
2
cables and blue connectors for 2,5 mm
2
ground cables (p/n
P-00084, P-00085) following the sequence shown in Figure 3.
Fig. 3 – Sequence of operations for shunt connections to the shaft line
NOTE
In general, the equipment that requires shunt connections are:
- Overrun
- Floor button panels
- Alarm sirens
- Shaft stop...
B.7.3. S
ERIES
C
ONNECTIONS TO THE SHAFT LINE
The series connections to the line (see the installation schematic diagram) must be performed
using the orange connectors following the sequence shown in Figure 6.
Pay particular attention to connect the last device of the series according to Figure 4, whereas the
first devices in the series should be connected according to Figure 5.
Fig.
4
Fig.
5
Last Connection in the Series
First Connection in the Series
NOTE
In general, the equipment that requires shunt connections are:
- Contacts for floor door open safety blocks
WIRE COLORS:
PINK
ORANGE
YELLOW / GREEN