3.12 INSTALLATION
CHECKLIST
(Photocopy this page to use as a worksheet)
□
Accessories:
confirm receipt as purchased with the AirPrep System.
□
Inspect AirPrep System:
check for possible damage during shipment. See Section 8.0
for inspection instructions.
□
Clean AirPrep ADS System:
remove handway cover and check for debris inside. If
Replace handway cover per instructions in Section 6.3.
□
CFM available:
determine available air supply (cfm) and record here.
Confirm AirPrep System capacity meets or exceeds the available cfm from above.
See Sections 3.2, 3.3, and 3.5 for information on determining air requirements.
□
Air inlet/outlet connection:
install air supply piping or connect an air supply hose that is
the same size as the air inlet size. See Section 3.4 for details.
□
Deliquescent (AirPrep ADS Systems):
fill dryer vessel with deliquescent tablets. See
Section 2.2 for capacity.
□
Breathing air:
provide Grade D air source for blast operators. See Section 3.9.
□
PPE:
provide all the necessary personal protective equipment. See Section 3.10.
□
Pressure relief valve:
install pressure relief valve if not provided on AirPrep System.
See Section 3.11 for information on pressure relief valve installation.
□
AirPrep System radiator drain:
for environments where freezing is possible install a
radiator drain ball valve to drain water that accumulates in the radiator.
Critical:
This
will protect the radiator from damage caused by inside water freezing. See Section 5.3.
□
Air motor lubricator:
fill lubricator with SAE #10 oil and set correct drip rate as
detailed in Section 7.2. Also see Sections 5.4, 5.6, & 8.5.4.
□
Air motor pressure regulator:
correct pressure is set by the manufacturer; however, to
ensure optimum operation confirm that it is set correctly. See Sections 5.5 and 11.2.
□
Electric power:
AirPrep Systems equipped with an electric motor that must be installed
by a qualified technician. Confirm the specified voltage to ensure proper installation.
Note:
motor starter thermal units are installed for the voltage specified at the time of
purchase; if the voltage is changed during installation risk of overload or under
protection will result. See Sections 3.7 and 5.7.
□
Install ground:
install earth ground. Electrically bond components. See Section 5.12.
□
Operator training:
all operators must completely read and understand the operation and
maintenance manual and be properly trained in equipment and blast operations.
□
AirPrep System Setup:
follow procedures in Section 6.1.
Summary of Contents for ACS 1200
Page 8: ...8 Copyright 2020 Axxiom Manufacturing Inc THIS PAGE IS INTENTIONALLY BLANK ...
Page 54: ...54 Copyright 2020 Axxiom Manufacturing Inc 9 2 a ACS 400 2500 Aftercooler System Air Motor ...
Page 62: ...62 Copyright 2020 Axxiom Manufacturing Inc 9 6 a ADS 400 2500 Air Dryer System Air Motor ...
Page 66: ...66 Copyright 2020 Axxiom Manufacturing Inc 9 8 a ADS 400 2500 Air Dryer System Electric Motor ...
Page 75: ...Copyright 2020 Axxiom Manufacturing Inc 75 NOTES ...