3.4.3 Filter heater, plug in
Two filter heaters are supplied in individual boxes. Connection cables have to be
plugged in for operation. Both filter heaters are identical and are operated only
while the gasflow is supplied into the bag.
1. Place both filter heaters at the lid of the rocking table with corresponding
magnets.
2. Guide the connection cable with plug through the cable port on the lid.
3. Plug in the LEMO plug of filter heaters into the BIOSTAT
®
CultiBag RM 600
as shown in the picture.
3.4.4 Aeration Tube
An Aeration tube is included with delivery to connect the air in filter of
CultiBag RM 600 with the BIOSTAT
®
RM Control Tower.
1. Place the aeration tube on the rocking table.
2. Guide the tube with plugs through the opening of rocking table at front side.
3. Connect the tube into the corresponding tube connectors at left side of
BIOSTAT
®
CultiBag Control Tower.
3.4.5 Connect Optical Fibre Cables
Two optical fibre cables are included with delivery to connect CultiBag RM 600L
with BIOSTAT
®
RM Control Tower.
1. Place both optical fibers cables on the rocking table.
2. Guide both optical fibers cable through the opening of rocking table at front side.
3. Connect the light fiber cables into the corresponding sockets at the rear side of
BIOSTAT
®
RM Control Tower.
Please refer to the associated manuals for Control Tower.
3.4.6 Connect Power Supply
1. Connect your power supply with BIOSTAT
®
CultiBag RM 600 system. Also please
refer to the sections on Power supply and Mains connection.
2. Connect your power supply with BIOSTAT
®
RM Control Tower.
Also please refer to the sections on Power supply and Mains connection.
3.4.7 Connect Pressurized Air, O
2
, N
2
1. Connect the gas supply lines to the gas inlet ports on the of BIOSTAT
®
RM
and CO
2
Supply
Control Tower 600.
All gas types (Air, O
2
, N
2
, CO
2
) need to be filtered and the inlet pressure reduced
to 1.5 bar g.
Please refer to the associated manuals for Control Tower.
Getting Started