Operating manual - ChillPAC and LP ChillPAC Mk 3
010823 en 2021.06
47/68
5.3.5
Restarting the chiller after power interruption
When the power supply returns after a short power interruption, restarting depends on the UniSAB III
settings.
If UniSAB III is set in AUTO running mode, the chiller will normally start up when needed by the auto-
matic control and when relevant timer/delay has expired.
If UniSAB III is set in MANUAL running mode, the operator must start up using the manual start key on
UniSAB III.
1.
Check variable set points
2.
UniSAB III must display: READY
3.
Follow the normal start-up procedure.
Note:
A long stop requires a
long-term stop
procedure as described in the following.
5.3.6
Restarting chiller unit after alarm stop (shutdown)
1.
Check and correct the cause of the alarm
2.
Reset the alarm
3.
UniSAB III must display: READY
4.
Follow the normal start-up procedure.
5.4
During operation
5.4.1
Checks to be performed during operation
1.
Choose a suitable picture from the UniSAB III display to view the data to be checked.
2.
Check that oil pressure is obtained and that the evaporating and condensing pressures are with-
in the permissible ranges.
3.
Check the other operating data.
4.
Check for abnormal noise and vibrations.
5.
Check the oil and refrigerant level.
6.
Make sure the chiller is operating stably - not fluctuating.
5.4.2
Monitoring of operation
To ensure satisfactory operation, it is required that you enter certain routines in a logbook on a regular
basis. You can use the items listed in the
Start-up log
, which is page 2 of the
Checklist
illustrated in
Fig. 24. The service engineer will need this information in connection with, for example, error reports.
In addition to the items listed in the start-up log, all other activities of service, maintenance or repair work
must be entered into your logbook as required by EN 378 and national laws.
Checklist
Along with this Operating manual we have provided a
Checklist
, as shown in Fig. 24, which will serve as
a help to the service engineer and
must be filled in during commissioning and start-up
.
Keep the filled-in checklist, and send a copy to Sabroe Factory as documentation that the unit has been
installed and commissioned correctly. The checklist will be required in case of a warranty issue.