4.2.2 Visual inspection and cleaning of tool attachment (every 2nd week)
The f ollowing maintenance activities should be carried out on the TA every 2
nd
week.
Action
Note
Check guide bushings
Check that the guide bushings
are greased. For cleaning and
lubrication see section 4.2.6.
Check that the guide bushings
are not worn-out or damaged.
For making replacements see
section 6.3.3.
Check servo power pins
Check that the servo power pins
are clean. For cleaning and
lubrication see section 4.2.6.
Check that the servo power pins
are not worn-out or damaged. If
worn-out or damaged replace
module, see section 6.3.10.
Check water/air couplings
Check that the couplings are
clean. For cleaning and
lubrication see section 4.2.4.
Check that the couplings, or the
module, are not worn-out, leaking
or damaged. For replacing
couplings see section 6.3.5. For
replacing the module, see section
6.3.11.
Check weld power pins
Check that the weld power pins
are clean. For cleaning and
lubrication see section 4.2.6.
Check that the weld power pins
are not worn-out or damaged.
For replacing weld pins, see
section 6.3.7. For replacing the
module, see section, 6.3.10.