![RMB/Energie neoTower Premium L Operating Manual Download Page 26](http://html1.mh-extra.com/html/rmb-energie/neotower-premium-l/neotower-premium-l_operating-manual_1467279026.webp)
26
Assembly
Operating manual neoTower® Premium L / 03.2017
4.3.9 Connecting the battery
A
Connect the batteries to the generation unit.
The batteries must be inserted in the battery boxes
provided.
4.3.10 Connecting the control cabinet
D
WARNING!
Risk of injury from electric shock.
The cables must be deenergised during assembly.
A
Deenergise the cables.
A
Ensure that the cables remain deenergised during
installation.
D
ATTENTION!
Risk of damage caused by the incorrect matching of
connectors.
Having the wrong polarity on the connection terminals can
seriously damage the control mechanism.
A
Ensure correct polarity on the connection terminals.
A
Connect the supply voltage to a right-rotating field.
All cables must be fed into the control cabinet through the
cable connections from underneath.
Use the enclosed wiring diagrams to identify the connection
terminals.
Wiring diagrams.
Please refer to the technical data for the permissible cross-
sectional areas of the supply lines.
D
“12.4 Technical data” (page 46).
It is necessary to observe the valid regulations (e.g. in
Germany the VDE directives).
A
Open the control cabinet.
A
Connect the temperature sensors (T1-T5).
A
Connect the modem.
A
Connect the batteries.