Installation & Servicing Instructions Rinnai Q-Series
58
13.4 Checking the O
2
The O
2
percentage is factory-set. This has to be checked at commissioning,
maintance and faults.
This can be checked by means of the following procedure:
- Remove the black cover of the gas valve by unscrewing the sealed screw.
-
Put the boiler into operation and take care that it can deliver its heat;
Tip: If there is no demand for heat on CH, turn the hot water tap completely open
and measure the O
2
.
-
Press the MODE-button for 5 seconds.
-
The display will show COdE followed by an arbitrary number;
-
Select by means of the + or the - button the code C123;
- Press the Store-button to confirm the code (code blinks 1 x);
-
Press the MODE-button until SERV is shown;
-
Press the STEP-button once until 1 is shown;
alternately 1 and OFF will be shown.
-
Calibrate the O
2
meter ;
-
Place the probe of the O
2
meter into the check point (see fig. 26);
-
Press the + button until the maximum value (in kW) is achieved;
The boiler will burn on full load (value on display in kW)
value in BTU/hr = x3415
-
Check the O
2
percentage:
Natural Gas: full load:
between 4.4% and 4.7%
min. load:
setting of full load +0.2% or greater
Propane:
full load:
between 4.8% and 5.1%
min. load:
setting of full load +0.2% or greater
Example:Full load set on 4.6% O
2
(natural gas) then the minimum load setting should
be 4.8% or greater.
Choose the right O
2
value according the kind of gas (Natural Gas or Propane
Gas). Wrong adjustment may result causing property damage, personal
injury or death.
-
Let the O
2
meter do its measuring procedure.
-
Adjust, if necessary, the adjustment screw to correct the O
2
value
(see fig. 27).
Ending the O
2
measuring procedure:
-
Press the - button until OFF is shown (keep button pressed).
With this the procedure has ended.
- Replace the black cover on the gas valve and fix it with the screw.
checkpoint CO
2
figure 26
adjustment screw CO
2
fig. 27
NOTICE
i
NOTICE
i
i
Summary of Contents for Q130SN
Page 18: ...Installation Servicing Instructions Rinnai Q Series 18 Boiler basic piping fig 6 ...
Page 44: ...Installation Servicing Instructions Rinnai Q Series 44 electrical ladder diagram figure 22a ...
Page 99: ...Installation Servicing Instructions Rinnai Q Series 99 ...
Page 119: ...Installation Servicing Instructions Rinnai Q Series 119 ...
Page 120: ......