Family Aqua Condens 3.5 BIS
10
A
4.3
Checks during and after the first commissioning
Following commissioning, check that the Family Aqua Condens 3.5
BIS, boiler performs the start-up procedures and subsequent shut-
down properly as described below:
- Press button 1,
(ON/OFF)
- Press button B, select heating water temperature, and turn the en-
coder A to select the desired value
- Press button C, select DHW temperature, and turn the encoder A
to select the desired value
- Generate a heat demand by acting on the room thermostat or
hourly timer (external)
- Also check the domestic hot water operation by opening a hot wa-
ter tap.
- Check the full stop of the boiler by turning off the system's main
switch.
After a few minutes of continuous operation, the binders and manu-
facturing waste will have evaporated, you can then perform:
- the supply gas pressure check
- the combustion check.
1
B
C
A
Supply gas pressure check
- Press button 1,
, to turn off the boiler
- Unscrew the fixing screws (D) of the connections cover
- Take out the connections cover by pulling it towards you (E-F)
- Undo the fixing screws (G) of the shell.
- move the housing base forwards and then upwards to unhook it
from the frame
- Lift the control panel and successively turn it forward
- Undo by two turns the screw of the pressure test point upstream
from the gas valve and connect the pressure gauge
- Power the boiler electrically by setting the main system switch to
“ON”
- Press button
(C)
- Turn the encoder A to max
- Fully open the hot water tap
- With the burner at maximum output, check that the gas pressure is
comprised between the minimum and rated power supply pressure
values indicated in the table
- Turn off the hot water tap
- Disconnect the pressure gauge and tighten the pressure test point
screw again upstream from the gas valve.
D
G
E
F
Pressure test point
upstream of the valve
Combustion check
- Access the “Calibration & Service” operations as indicated in the
specific chapter
- Insert the analyser probes in the prescribed positions on the air
box after removing the screws H and the cap I.
- Check in parameters HH and LL that the CO
2
values correspond to
those indicated in the table.
DESCRIPTION
GAS
METHANE
(G20)
LIQUID GAS
PROPANE
(G31)
Max. CO
2
9,0
10,0
%
Min. CO
2
9,5
10,0
%
- If the reading is different, modify as indicated in section HH and LL
of the "Settings" chapter.
- Perform the combustion check.
Then:
- remove the analyser probe and close the combustion analysis inlet
- Close the instrument panel and reassemble the cover in the re-
verse order compared to the disassembly description.
When the checks are completed:
- Press the
key to select the type of operation.