❷ Do the
standard bolt-installation (SBI)
of the motor gearbox on the applicable mounting plate
or an alternative.
Minimum Screw-in depth (SID)
•
For the tightening torque of the used fixing bolts a
minimum
screw-in depth
(SID)
is necessary.
Refer to the illustrations (Standard Bolt-Installations [SBI]) that follow.
•
Possibly fixing bolts with more length are necessary if a larger sheet thickness is used!
•
Tighten the bolts crosswise and gradually with the correct tightening torque (
Nm
).
Standard Bolt-installations (SBI)
Make sure that the drive unit is installed in a stable condition. The
structure must have sufficient strength for the applied forces.
Make sure that easy access to the cover of the RW motor-gearbox is
possible for all work.
Installation OUTDOORS of RW motor-gearboxes is only permitted
with PROTECTION from RAIN (protection covers or such) at a
minimum temperature of 0 °C. Problems with moisture and/or the IP
protection rating (if applicable) must be prevented.
SID (2x):
≥ 11 mm!
M10 x 20 (2x)
M10 (2x)
45 Nm
RW45–800
SID (4x):
≥ 14 mm!
SID (3x):
≥ 16 mm!
M10 x 25 (3x)
M10 (3x)
M12 x 25 (4x)
M12 (4x)
- 45 Nm
- 80 Nm
Ridder Drive Systems B.V.
T
+31 (0)341 416 854 -
F
+31 (0)341 416 611 -
I
21