smooth connection without
stretching the pipe. Use the spring
clips to secure in place.
6.8 The other pipe that comes out of the
venturiT™ should now be connected
to the top of the Type AA airgap
drain. Cut it back if to a sensible
length but not so short that it is
stretched. The pipe should run down
hill so that water can escape by
gravity.
6.9 Using the
fi
nal piece of silicon in the
fi
tting kit connect the front spigot (this
feeds chilled and sparkling water) to
the remaining pipe coming from the
spout – remember to push up onto
the pipe - don’t pull it down.
————————————————————
DO NOT TURN ON THE POWER
This step is handled in the commissioning
guide.
NOTE
The venturiT™ is a unique device that
enables the boiler to vent itself to drain.
During the heating cycles, water
expansion would otherwise push boiling
water out of the spout without activating
the boiling function. It’s essential to install it
running the pipe down-hill.
NOTE
If using an RO system you must ensure it
delivers water at 45-60psi at all times. You
may need to add a pump to ensure the
optimum psi is supplied to the Quatreau
system.
During commissioning use only mains
water then convert to RO once the system
has been set up and commissioned.
————————————————————
————————————————————
#7 INSTALLING THE QUATREAU CHILLER
CARBONATOR
————————————————————
7.1
Site the chiller unit to the eft of the
Boiler over the ventilation duct
7.2
Use the 1/4” PE pipe provided to
interconnect the QST553-B and CS20
units as follows.
7.2.1 H2O OUT on the 553-B into WATER IN
on the chiller
7.2.2 CO2 OUT on the 553-B into CO2 GAS
IN on the chiller
7.2.3 SODA WATER OUT on the chiller to
CARB IN on the 553-B
7.3.4 STILL WATER OUT on the chiller to
CHILLED IN on the 553-B
————————————————————
NOTE
Inside the
fi
tting kit are 4 ¼” stem elbows
that can be inserted into the chiller to
make it easier to install the
interconnections without kinking the pipe
NOTE
Ensure that you leave a 1” gap around the
sides of the chiller unit - this enables
ventilation and air movement without
which the system will not chill correctly.
DO NOT TURN ON THE POWER
TO THE CHILLER OR DAMAGE
WILL OCCUR.
This step is covered in the commissioning
guide.
End of installation guide. Now refer to
commissioning guide.
————————————————————