4 Electrical connection

4.4 After installation

  Ensure that all necessary safety and functional tests 

have been carried out according to applicable 
standards.

Note! Module damage may occur!

  Ensure that the plug connections are secured away 

from any water-channelling surface. 

  Integrate the system into the existing lightening 

protection system in accordance with the applicable 
local regulations.

Warning! Fire Risk!

  Do not use light concentrators (e.g. mirrors or lenses).

  Ensure that the cabling is not exposed and / or 

hanging and is protected from dirt, moisture and 
mechanical friction.

5 Grounding

Protective Grounding

In order to prevent electrical shock or fire, the frame of the 
module as well as any non-current-carrying metal parts of the 
system must be grounded. While this section provides some 
information about grounding the Qcells frames and modules, 
reference should be made to local statutes and regulations for 
specific requirements on grounding. The U.S. National Electrical 
Code addresses these issues in Article 250. A module with 
exposed conductive parts is considered to be in compliance 
with this standard only when it is either electrically grounded 
in accordance with the manufacturer’s instructions and the 
requirements of the National Electrical Code, ANSI / NFPA 70 
(2014-2017), or when the bonding means has been evaluated with 
this module to UL 2703.

Proper grounding is achieved by bonding all exposed non-
currentcarrying metal equipment to the appropriately sized 
equipment grounding conductor (EGC) or racking system that can 
be used for integrated grounding.

Qcells frames are protected from corrosion with an anodized 
coating, which has to be penetrated in order to ensure proper 
bonding. The different methods listed below are suggested 
methods for an appropriate bond between the frame and the 
EGC or racking system (that will have to be properly grounded). 
The method appropriate for any individual installation will depend 
on multiple factors.

 

Dimensions shown are in inches.

0.177” (+0.008/-0)

±0.08

0.79”

0.47”

±

0.08

Option A: Use of a grounding lug

A listed grounding lug can be bonded to the frame using the 
grounding holes pre-drilled in the frame. These holes are 
marked with a ground symbol, as shown below on the frame 
section drawing: To install the grounding lug, follow the specified 
instructions of the manufacturer. The grounding lug should be 
made of stainless steel or tin plated metals such as aluminum to 
avoid corrosion.

The grounding lug should be attached to the frame grounding 
hole using a stainless steel screw, toothed lock washer or KEPS 
nut (in order to penetrate the anodized layer) and backing nut. 
Care should be taken to avoid the use of grounding hardware of 
dissimilar metals, which may lead to corrosion.

Option B: Integrated grounding methods

The Qcells modules can be bonded with the racking system 
using UL1703 or UL2703 certified integrated grounding methods. 
The racking system will then have to be grounded so that the 
overall system is properly grounded. The listed racking system 
and grounding device should be installed in accordance with 
the manufacturers’ instructions. An example of such integrated 
grounding method is the use of a WEEB clip or Schletter plate 
between the module and the racking system, when mounting the 
module.

The WEEB washers are generally compatible with Qcells 
modules, however each combination module / racking system 
requires a specific WEEB washer size. Note that WEEB clips 
are intended for single use only; they must not be reused after 
removal or loosening. Refer to Wiley’s installation instructions for 
the specific use of WEEB washers.

An example of such integrated grounding method is the use of a 
washer recognized as meeting UL2703 requirements between 
the module and the racking system, when mounting the module. 
For example, WEEB washers are generally compatible with Qcells 
modules, however each combination module / racking system 
requires a specific WEEB washer size. Note that WEEB washers 
are intended for single use only; they must not be reused after 
removal or loosening. Refer to Wiley’s installation instructions for 
the specific use of WEEB washers.

 

Dimensions shown are in inches.

PV Laminate

Backing Nut (Stainless Steel)

Toothed Lock Washer (Stainless 
Steel)

Grounding Lug (Stainless Steel 
or tin-plated metal)

Equipment 
Grounding 
Conductor

Aluminum 
Frame

Screw (Stainless Steel)

Summary of Contents for Q.PEAK DUO XL-G11.X / BFG Series

Page 1: ...Installation and operation manual Q PEAK DUO XL G11 X BFG solar module series...

Page 2: ...d solar module operator are responsible for compliance with all applicable statutory requirements and regulations The following regulations and standards must be upheld at all times during the install...

Page 3: ...ALLATION OR CONFIGURATION IMPROPER MAINTENANCE UNINTENDED USE AND UNAUTHORIZED MODIFICATION Attention This marking indicates that this product should not be disposed of with other household waste with...

Page 4: ...the following applications Operating temperatures from 40 F to 185 F Pull loads and push loads according to chapter 2 3 Test Load in accordance with IEC 61215 and Design Load 1 5 in accordance with U...

Page 5: ...s FB1 4 mounting slots 20 508 FB2 4 mounting slots 20 508 mFB2 20 508 Tracker installation on mounting points TB1a 39 7 1008 TB1b 32 813 39 7 1008 TB2a 20 or 32 or 39 7 508 or 813 or 1008 TB2b 32 813...

Page 6: ...acer allowed between the module and substructure CL1a FB1 These mounting options are not recommended as mounting rails will cast shade on the module rear side FB1 FB2 TB1a TB1b TB2a TB2b mFB2 Use M8 c...

Page 7: ...erter into account when determining the maximum number of modules in the string Parallel Connection Modules may be damaged by the occurrence of reverse currents caused by module defects ground leaks o...

Page 8: ...upright and horizontally as shown Note Module damage may occur Never step on modules Do not subject modules to any mechanical stress Do not allow any objects to fall onto modules 3 Installation 3 2 Pr...

Page 9: ...may result from the separation of a closed circuit These can result in life threatening injuries The danger increases when several modules are connected in series Please be aware of that the entire op...

Page 10: ...of fatal injury due to electric shock Electrical work may only be performed by qualified and skilled personnel see page 3 Ensure correct polarity 4 Electrical Connection 4 3 Connection of modules Use...

Page 11: ...0 0 8 0 0 08 0 79 0 47 0 08 Option A Use of a grounding lug A listed grounding lug can be bonded to the frame using the grounding holes pre drilled in the frame These holes are marked with a ground sy...

Page 12: ...Risk of falling due to unsecured access Never access the installation area alone or without taking adequate security precautions Please commission a trade specialist NOTE Module surface damage may occ...

Page 13: ...nstallation manual solar modules Q PEAK_DUO_XL G11 X BFG_modules_series_2022 07_Rev01_NA HANWHA Q CELLS AMERICA INC 400 Spectrum Center Drive Suite 1400 Irvine CA 92618 USA EMAIL WEB TEL hqc inquiry q...

Reviews: