2 Planning

2.4 Electrical Layout

Module Selection

For detailed key electrical data, please refer to the actual data 
sheet referring to the relevant Module (available at www.qcells.
com).

  For maximum energy yields, mismatches of specified electric 

current (I

MPP

) of more than 5 % should be avoided for all 

modules connected in series.

Safety Factor

During normal operation, a module may generate a greater 
current and / or higher voltage than that determined under 
standardized test conditions. Accordingly, the values of I

SC

 and 

V

OC

 marked on the module should be multiplied by a facot of 1.25 

when determining:

 

the component voltage ratings,

 

conductor ampacities,

 

fuse sizes,

 

size of controls connected to the PV output.

Refer to Section 690-8 of the National Electrical Code for an 
additional multiplying factor of 125 percent (80 percent derating) 
which might be applicable.

  Please follow the valid national guidelines for the installation 

of electrical systems (refer to section 690-8 of the NEC for 
an additional multiplying factor of 125 percent [80 percent 
derating] which may be applicable).

Series Connection

Connection of modules in series is only permitted up to the 
maximum system voltage as listed in the applicable data sheet.

  Take into account all possible operating situations and all 

relevant technical norms and regulations when designing the 
system. It has to be ensured that the maximum system voltage, 
including all necessary safety margins, is not exceeded.

  Take the voltage limit of the inverter into account when 

determining the maximum number of modules in the string. 

Parallel Connection

Modules may be damaged by the occurrence of reverse currents 
(caused by module defects, ground leaks, or defective insulation).

  Ensure that the maximum reverse current load capacity 

indicated in the data sheet is met.

In order to limit reverse currents that may occur, we recommend 
using the following safety options:

1) Layout with a limited number of parallel connected strings :

Without undertaking further current blocking measures, a maxi-
mum of two module strings may be operated in parallel on a sing-
le inverter or MPP tracker.

2) Layout with string fuses :

Use overcurrent devices (e.g. fuses) according to the relevant 
standards in each string. Use gPV-fuses according to IEC 
60269-6. Observe the maximum permitted number of strings as 
indicated in the specifications provided by the respective string 
fuse manufacturer and the technical guidelines.

NOTE!

When installing different product versions, the lowest minimum 
permitted reverse current load capacity applies.

Inverters

Inverters with or without transformers may be used.

3 Installation

3.1 Safety and Transport

  Leave modules in their original packaging until 

installation.

  Store the modules securely in cool and dry rooms. 

The packaging is not weatherproof.

  Inspect the packaging for damages.
  Contact the transport company regarding any 

damage to the packaging and follow their 
instructions.

  Follow any instructions on the packaging.

  Ensure that all personnel are aware of and adhere to 

accident-prevention and safety regulations.

  While working wear clean gloves.

Danger! Risk of fatal injury due to electric shock!

  Do not install damaged modules.
  Inform your distributor of any damages immediately.

Warning! Fire Risk!

  Do not install modules indoors.
  Do not install modules on moving objects.

§

GB

§

I

§

D

Summary of Contents for Q.PEAK DUO XL-G11.X / BFG Series

Page 1: ...Installation and operation manual Q PEAK DUO XL G11 X BFG solar module series...

Page 2: ...d solar module operator are responsible for compliance with all applicable statutory requirements and regulations The following regulations and standards must be upheld at all times during the install...

Page 3: ...ALLATION OR CONFIGURATION IMPROPER MAINTENANCE UNINTENDED USE AND UNAUTHORIZED MODIFICATION Attention This marking indicates that this product should not be disposed of with other household waste with...

Page 4: ...the following applications Operating temperatures from 40 F to 185 F Pull loads and push loads according to chapter 2 3 Test Load in accordance with IEC 61215 and Design Load 1 5 in accordance with U...

Page 5: ...s FB1 4 mounting slots 20 508 FB2 4 mounting slots 20 508 mFB2 20 508 Tracker installation on mounting points TB1a 39 7 1008 TB1b 32 813 39 7 1008 TB2a 20 or 32 or 39 7 508 or 813 or 1008 TB2b 32 813...

Page 6: ...acer allowed between the module and substructure CL1a FB1 These mounting options are not recommended as mounting rails will cast shade on the module rear side FB1 FB2 TB1a TB1b TB2a TB2b mFB2 Use M8 c...

Page 7: ...erter into account when determining the maximum number of modules in the string Parallel Connection Modules may be damaged by the occurrence of reverse currents caused by module defects ground leaks o...

Page 8: ...upright and horizontally as shown Note Module damage may occur Never step on modules Do not subject modules to any mechanical stress Do not allow any objects to fall onto modules 3 Installation 3 2 Pr...

Page 9: ...may result from the separation of a closed circuit These can result in life threatening injuries The danger increases when several modules are connected in series Please be aware of that the entire op...

Page 10: ...of fatal injury due to electric shock Electrical work may only be performed by qualified and skilled personnel see page 3 Ensure correct polarity 4 Electrical Connection 4 3 Connection of modules Use...

Page 11: ...0 0 8 0 0 08 0 79 0 47 0 08 Option A Use of a grounding lug A listed grounding lug can be bonded to the frame using the grounding holes pre drilled in the frame These holes are marked with a ground sy...

Page 12: ...Risk of falling due to unsecured access Never access the installation area alone or without taking adequate security precautions Please commission a trade specialist NOTE Module surface damage may occ...

Page 13: ...nstallation manual solar modules Q PEAK_DUO_XL G11 X BFG_modules_series_2022 07_Rev01_NA HANWHA Q CELLS AMERICA INC 400 Spectrum Center Drive Suite 1400 Irvine CA 92618 USA EMAIL WEB TEL hqc inquiry q...

Reviews: