RCS Climbing Device and Hydraulics
Assembly Instructions
Part C Maintenance
Fig. 19: Plug Socket RCS
Fig. 20: Adapter Cable RCS
C2 Commissioning
C2.1 Measures taken during
commissioning
– Listen out for any pump noises after
starting up.
– Check the rotary field.
– Check level of the hydraulic oil and
top up if necessary.
– Check temperature of the electric
motor.
– Check temperature of the hydraulic oil
and, if necessary, bring to operating
temperature, see C3.4.
– Check filter and, if necessary, clean
or replace.
– Carefully vent the system during initial
commissioning or after intermediate
storage, see D5.2.
– Check the functionality of the hand
valve and hydraulic cylinder.
– Check components and connections
for signs of external leakage.
– Never re-torque leaking screw
connections under high pressure,
but only after a pressure release!
C2.2 Electrical connection
Connection carried out only by
authorised qualified personnel.
Accessories:
– Plug Socket RCS Item no. 110279
(S/N: K016.440) for connection plug
on the pump.
– Adapter Cable RCS Item no. 110280
(S/N: SK050316BX) for operating
voltage 400 V and a power supply line
with CEE coupling 16 A.