Fill with coolant
Filling quantity about11 litres.
Img.3-1:
Coolant level indicator
3.8
First commissioning
WARNING!
The machine may only be commissioned after proper installation.
There is a danger to persons and equipment, if the first commissioning carried out by
inexperienced personnel. We do not assume any liability for damages caused by
incorrectly performed commissioning.
ATTENTION!
Before initially operating the machine, check all screws, fixtures and/or safety devices
and tighten up the screws if necessary!
WARNING!
Risk from using improper workpiece clamping materials or operating the machine at an
inadmissible speed.
Only use the tool clamping devices (e.g. lathe chuck) that were delivered with the
machine or those offered by OPTIMUM as optional equipment.
Only use tool clamping devices in the intended admissible speed range.
3.9
Electric three-phase connection
Connect the electrical supply cable. The connection points are at the terminal block for the
main switch and are marked with L1, L2, L3.
Check the fusing (fuse) of your electrical supply according to the technical instructions
regarding the total connected power of the Drehmaschine.
Main Fuse 16A.
ATTENTION!
Ensure that all 3 phases (L1, L2, L3) and the ground wire are connected correctly.
The neutral conductor (N) of its power supply is not connected.
ATTENTION!
Make sure that the direction of rotation of the drive motor and cooling lubricant pump is
correct. If the rotational direction switch is switched to the down position, the lathe
spindle must rotate anticlockwise. If necessary, two phase connectors at the three phase
Level indicator
Outlet
Coolant pump