OMNI 4000/7000 Operations and Maintenance Guide
– Rev F
6-5
Front Panel Operations
6.3
Proving Functions
6.3.1 Manual Prove Request
To manually request a prove, follow these instructions:
1.
a. In the
Home
menu, use the arrow
navigation keys to go to and
select
Prove
.
b. Press the
OK
key.
2.
a. Use the
Right
or
Left
arrow keys to
select the Meter Run (at the top of the
screen) for which you need to run
a prove.
b. Press the
Prove
function key to start
the prove sequence.
3.
Press the
Abort
function key at any time to
stop the prove, if needed.
If a prove is active on a different Meter Run, you will see this temporary message.
4.
If you need to run a prove on a different
Meter Run, use the
Right
or
Left
arrow
keys to select a different Meter Run at the
top of the screen.
The
Status
field shows the status
of the prove as it progresses. Go to
Section 3.5.3 for more information
on prove status messages.