31
communication address as page 42: Set the EPS as page 36:
Shutdown inverter
For maintenance or other service work, the inverter must be switched off.
Proceed as follows to disconnect the inverter from the AC and DC power
sources, Lethal voltages or damage to the inverter will follow if otherwise.
·
Disconnect the external AC circuit breaker and secure it against reconnection.
·
Rotate the DC switch to the "OFF" position for disconnecting all the PV string
inputs.
·
Wait about 10 minutes until the capacitors inside the inverter completely
discharge.
·
Ensure that the DC cable is current-free via a current clamp.
NOTE!
Please set the inverter if it is the first time to start up. Above steps is
for the regular start-up of the inverter, lf it is the first time to start up
the inverter you need to start up the inverter
WARNING!
Danger of burns!
Even if the inverter is shut down, it may still be hot and cause
burns. Wear protective gloves before operating the inverter after it
cools down.
Summary of Contents for BRE-I-5K
Page 1: ...1 User Manual BRE I 5K OLIPOWER ENERGY AUTOMATION TECHNOLOGY...
Page 28: ...28 1 ADD Interface ADD interface PINS definition...
Page 33: ...33...
Page 34: ...34...
Page 54: ...54 Reactive power setting After user log into the system Remote control Reactive power...
Page 55: ...55 Volt watt setting After user log into the system Remote control Australia...
Page 62: ...62...