SKS - Steam to Steam Humidifier
Installation Instructions and User Manual
15
Stage 3 – Pipework for HTHW / Raw Steam
HTHW / Raw steam supply piping must conform to local codes and regulations.
Risk of Distortion and Failure. HTHW / Raw steam piping installation must be
supported so that no strain are imposed on the Humidifier steam inlet and control
valve.
Pipes must be inspected for dirt and chips after threading and reaming the end of
pipes.
After installation, field piping and Humidifier piping must be checked for leak.
All leaks MUST be sealed prior to commissioning the Humidifier.
Union Dimensions &
Installation
Model
HTHW / Raw steam
inlet
Return
outlet
SKS-100/130-SLP
Ø20mm
Ø20mm
SKS-190/290-SLP
Ø25mm
Ø20mm
SKS-390-SLP
Ø32mm
Ø20mm
SKS-500/690-SLP
Ø32mm
Ø32mm
SKS-950-SLP
Ø40mm
Ø40mm
SKS-1250-SLP
Ø32mm (x2)
Ø32mm (x2)
SKS-200-CHP
Ø20mm
Ø20mm
SKS-333-CHP
Ø32mm
Ø32mm
SKS-667-CHP
Ø32mm (x2)
Ø32mm (x2)
SKS-1250-SLP
and
SKS-667-CHP
is equipped with two (2) heat
exchangers and therefore has 2 HTHW / raw steam inlets and two (2)
condensate return outlets.
Typical HTHW Installation
HTHW Supply Size
The size of the HTHW supply pipe and the control valve must be calculated
considering
0.8kW of HTHW for each kg of clean steam
produced and
distributed into the AHU.
(Fig. 14)
!
Isolating valve
Isolating valve
3 way Actuated Control
valve (diverting)
SKS
Thermometer
Return line
Supplied by others
RETURN
Thermometer
Regulating valve
HTHW