Nederman start and control units have the terminals connected, and in some cases jumped
connections. Verify the connections using the connecting diagrams.
•
The pilot signal cable from all valves is linked to the start and control unit on units with
automatic start/stop.
•
All valves at work sites are closed.
8.2
Initial start-up
8.2.1 Checking the direction of rotation
At initial start-up, check the direction of rotation by doing the following:
1.
Start the unit.
2.
Compare the direction of the motor rotation with the arrow on the motor.
•
If the direction of the motor and the arrow are the same, allow the starting procedure to
continue.
•
If the direction of the motor is different from the direction of the arrow, change the
direction of the motor by doing the following:
1)
Stop the unit.
2)
Disconnect power.
3)
Open the start and control unit
4)
Switch two of the incoming phase conductors.
8.2.2 Checking the Y/D time setting
NOTE!
The Y/D time setting is factory preset and does not normally need to be adjusted.
Switching to D mode before the motor has reached full speed can damage the start and control
unit. This is particularly important when automatic start and stop is installed. Too long in Y
mode results in an unnecessary delay before the unit delivers full vacuum.
At initial start-up check the Y/D time setting by doing the following:
•
Make sure the motor sound is constant and high pitched, indicating full motor effect, before
the motor switches to D mode.
8.2.3 Checking the start-up and vacuum limiting valve
Perform the following start-up and vacuum limiting valve at initial start-up to check that the
valve works correctly:
1.
Start the unit.
2.
Place your hand on the motor cooling air outlet, Figure 3 item 16.
3.
The valve works correctly when:
–
Air is sucked into the outlet silencer during Y mode.
–
Hot air is blown out from the outlet silencer during D mode.
8.2.4 Checking the vacuum level
At initial start-up ensure the vacuum level is at correct level by doing the following:
•
Check that the vacuum level on the vacuum meter, Figure 3 item 15, corresponds the
specified levels in ‘Table 4-1: Technical data’. See Section ‘9.11 Vacuum level’ for more
information about checking the vacuum level.