XR6/XR3 Operations and Maintenance Manual
Test and adjustment
Issue 3.1 2013-03-14
Page 5-1
Section 5:
Test and adjustment
This section contains test and adjustment procedures for the XR6/XR3 transmitter. The test
procedures use integral meters and precision test/monitoring equipment. The test procedures
contain routine adjustment instructions to bring the parameter being tested within defined limits,
where appropriate.
Follow all instructions in the order presented, particularly for personnel who are not familiar with
detailed circuit theory and may not realize the impact a specific adjustment can have on other steps.
These adjustments should be performed during initial turn-on and after major repairs or a frequency
change.
Test equipment required
To perform the procedures outline in this section you will need:
•
a 50
Ω
dummy load that is able to dissipate the RF power being applied to it (6 kW carrier, 9
kW total)
•
an oscilloscope
•
a digital multimeter
•
an audio signal generator
•
a modulation monitor
Test prerequisites
Complete the following steps before performing any testing or adjustment procedures:
1. Verify that nothing affecting the RF power stage has been changed since the initial start-up
procedure (see
of the
XR6/XR3 Installation Manual
) was
completed.
2. Switch off the ac power at the service entrance.
Summary of Contents for XR6
Page 2: ......
Page 4: ......
Page 10: ...XR6 XR3 Operations and Maintenance Manual Page x Issue 3 1 2013 03 14...
Page 18: ...XR6 XR3 OPERATIONS AND MAINTENANCE MANUAL PAGE XVIII VERSION 3 1 2013 03 14...
Page 65: ...XR6 XR3 Operations and Maintenance Manual Using the event log Page 3 8 Issue 3 1 2013 03 14...
Page 71: ...XR6 XR3 Operations and Maintenance Manual Routine maintenance Page 4 6 Issue 3 1 2013 03 14...
Page 82: ......