j.

Remove any dirt from the floor sockets,
pivot boxes and bottom door closers

k. Ensure that any lock and profile cylinder

can be moved easily

l.

For single/double action sliding panels,
check position of the reversing gear

GLASS INSTALLATION AND GLAZING

 

This section applies only if you need to install glass for 
any reason.  Proper glass installation is critical, as, with the 
NanaWall single track sliding system, glass is a structural 
part of the panel.

Glass, with appropriate dimensions, thickness and

 

specifications will be needed. Depending on the model,

 

widths of all glass panels may not be equal. 

Contact 

NanaWall for the glass dimensions. Please note that glass 
is required to be safety glass – either fully tempered or 
laminated as specified for a particular order. Check with 
all applicable codes and regulations.

Glass shall meet the current requirements of ASTM C 
1306 “Standard Specifications for Flat Glass” for quality, 
thickness and dimensional tolerances. Tempered float 
glass shall meet the current requirements of ASTM C 
1048 “Standard Specifications for Heat-Treated Flat 
Glass - Kind HS, Kind FT Coated and Uncoated Glass.” 
All tempered glass shall have a permanent logo, which 
signifies Safety Commission 16 CFR-1201 and the safety 
glass test requirements of ANSI Z 97.1 (current editions) 
or other equivalent safety standards.

Follow all proper applicable glass installation and glazing 
techniques as recommended in the Flat Glass Marketing 
Association (FGMA) “Glazing Manual” and “Sealant 
Manual”. Always use suction cups to shift glass within an 

opening. The panels would need to be removed from the 
opening to install the glass.  Panels can be laid flat on 
sawhorses.  

Please get in touch with NanaWall before you replace 
a glass pane in order to get the right material and 
instructions to glaze the panel!

Summary of Contents for HSW75

Page 1: ...ingle Track Sliding Frameless System This manual is to be used by the installer for installation and is to be kept by the Owner for reference Replacement parts can be ordered directly through NanaWall...

Page 2: ...s of glass The NanaWall glass thickness for the panels is based on the Glass Association of North America GANA recommended minimum glass thickness for fully tempered Interior butt glazed fixed glass p...

Page 3: ...E OF A 5 PANEL UNIT Panel 1 sliding panel Panel 2 sliding panel Panel 3 sliding panel Panel 4 sliding panel Panel 5 double action end panel non sliding with pivot box or double action end panel non sl...

Page 4: ...lean and dry location and protect against defacement or damage especially to the edges of panels PREPARATION OF THE OPENING AND SUPPORT STRUCTURE ABOVE Make rough opening width at least 1 2 wider than...

Page 5: ...lable please verify the type of sockets for this order If planning to cut into a post tensioned concrete for bottom door closers pivot boxes and sockets a structural engineer and architect has to be c...

Page 6: ...ews provided See Sheet 4 of the Installation Manual Make sure that the correct angles between segments are maintained and that the transitions between the track segments are perfectly aligned and smoo...

Page 7: ...FORCED TO ENSURE THAT THE UPPER TRACK IS NOT BOWED Upper track segments must be joined such that they are even tight and aligned perfectly Otherwise the running carriages may wear out prematurely whic...

Page 8: ...E HAS TO BE SECURED TO THE SOCKET IN THE PIVOT BOX IN THE FLOOR BEFORE THE SINGLE DOUBLE ACTION SLIDING PANEL CAN FUNCTION PROPERLY OTHERWISE IT WILL NOT BE STABLE AND CAN FALL AND HURT SOMEBODY C GAP...

Page 9: ...hanism is not in the way Make sure the panels are straight and the correct 4 mm gap between panels is maintained Start with the panel furthest away from the parking bay and add blue masking tape under...

Page 10: ...6 52 mm Please check custom product drawing for swing direction inside outside See Sheet 14 and 15 of the Installation Manual Mark this point and if concrete use a diamond core drill bit with 1 1 4 di...

Page 11: ...ip to the edge of the wall Make sure that the full underside of the box rests on a flush and level surface and fix it temporarily into place Then install the receiver box for the top axle by hanging i...

Page 12: ...ed Check if all angles are correct Each leg of the stacking bay track should be equidistant at all points Step F5 Correct any problems before you finish the trimming Do not attach any trimming directl...

Page 13: ...n edge bolt with hand or foot d Automatic Locking when adjacent panels are pulled together and properly aligned the bolt automatically engages 4 Note that there is a carrier at each upper corner of a...

Page 14: ...e head track and engages to the top rail Turn about 8 10 revolutions in a clockwise direction until there is a slight resistance 3 Release the Quick Release Lock on the pivot side to disengage the loc...

Page 15: ...ce Its appearance may be marred by harsh chemicals abuse or neglect Frequency of cleaning depends on exposure and needs For aluminum surfaces generally warm soapy water should be sufficient Stubborn s...

Page 16: ...licable codes and regulations Glass shall meet the current requirements of ASTM C 1306 Standard Specifications for Flat Glass for quality thickness and dimensional tolerances Tempered float glass shal...

Page 17: ...soap and fresh water at least every month and more frequently if necessary After washing the surface should be rinsed thoroughly with clean water and allowed to dry For cleaning do not use abrasive h...

Page 18: ...antial cracking chipping or peeling due to the deterioration of the finish exclusive of mechanical damage 2 chalking in excess of a numerical rating of 8 as per ASTM D 659 or 3 fading or color changes...

Page 19: ...e of the affected product in full satisfaction of its obligations Wood Wood components must be properly finished on all sides promptly after receipt of unit before installation of unit and prior to ex...

Page 20: ...Product selection application storage handling modification or waterproofing Movement of surrounding substrates including deflection of the header of more than or any other stresses on product Instal...

Page 21: ...faces Acts of God falling objects fire accidents external forces or other conditions beyond NanaWall s control Gas fill or retention levels in insulated glass units Field testing of Product Performanc...

Page 22: ...___________________________________ Project Address if different from above _____________________________________________________________ INSTALLATION Installer Name _______________________________ Ad...

Reviews: