THREE YEAR COVERAGE.

 

For three (3) years from Delivery, NanaWall will respond as follows:

Anodized Surface Finish of Aluminum Profiles.

 For anodized surface finish of aluminum profile not functioning as 

an ESM,* NanaWall will, at its option, (1) assume reasonable costs to restore the finish on a non-compliant (non-ESM) 
material using standard commercial refinishing techniques or (2) ship a replacement part.

ONE YEAR COVERAGE.

 

For one (1) year from Delivery, NanaWall will respond as follows:

Screens.

 For a screen part (excluding the screen mesh) with a material or workmanship issue that substantially impairs 

the function of the screen, NanaWall will, at its option, (1) ship a replacement screen or (2) upon return by owner, repair 
the screen without charge.

ADDITIONAL SERVICE INFORMATION

This Warranty does not cover labor costs to remove existing parts or products, install a replacement part or product, costs 
to finish wood products, or the cost to repair or replace surrounding substrates, trim, or other work. Nor does it cover 
costs incurred due to delays or other construction costs, costs for late or damaged delivery, loss of revenue, loss of time, 
liquidated damages, inconvenience, or loss of use of the product or any parts or components. NanaWall reserves the right 
to determine whether or not a covered condition exists. If the claim is not covered under this Warranty, NanaWall may 
charge and collect a fee for on-site product inspections.

Any replacement part or product will be shipped to the location of original product delivery by NanaWall. Replacement 
products will be the closest equivalent current product and may not be an exact match to the original. If providing a 
replacement part or product is not commercially practicable, NanaWall may elect to refund the purchase price of the 
affected product in full satisfaction of its obligations. 

Wood.

 Wood components must be properly finished on all sides promptly after receipt of unit before installation of unit, 

and prior to exposure to weather. Repair or replacement of a warped wood panel or frame can be delayed by up to 12 
months from date of claim to allow the wood component to adjust to local environmental conditions. 

Glass.

 Unloading the replacement glass/panel from the delivery truck is the responsibility of the owner. Due to the 

weight of the product, appropriate manpower and/or equipment will be needed to unload and move the glass/panel to 
the location for replacement. Depending on the size of the replacement part and interior building dimensions, it may not 
be possible to transport the glass/panel through the interior of the building. NanaWall is not responsible for any costs 
associated with moving the replacement glass/panel at the delivery location.

**Whether an installer is an independent NanaWall Certified Installer or Approved Installer is determined by the installer’s 
status as of the date of delivery. NanaWall maintains information regarding the installers designated as Certified Installers 
or Approved Installers.

NOTICE PROCESS

Written notice of any claim under this Warranty with supporting documents such as photos or videos must be given to 
Nana Wall Systems, Inc. via email to [email protected] or via mail to 100 Meadowcreek Drive, Corte Madera, CA 
94925, promptly when discovered. A condition will not be covered under this Warranty if there is a failure to notify 
NanaWall in writing (1) within 7 days of receipt of the product for any defect which an ordinary inspection would reveal, 
(2) within a reasonable time during the warranty period after an impairment in operation and use is manifest or a hidden
defect is discovered, or (3) for claims first made after expiration of the coverage period outlined in this Warranty.

NANAWALL LIMITED WARRANTY

PAGE 2 OF 4

Summary of Contents for HSW75

Page 1: ...ingle Track Sliding Frameless System This manual is to be used by the installer for installation and is to be kept by the Owner for reference Replacement parts can be ordered directly through NanaWall...

Page 2: ...s of glass The NanaWall glass thickness for the panels is based on the Glass Association of North America GANA recommended minimum glass thickness for fully tempered Interior butt glazed fixed glass p...

Page 3: ...E OF A 5 PANEL UNIT Panel 1 sliding panel Panel 2 sliding panel Panel 3 sliding panel Panel 4 sliding panel Panel 5 double action end panel non sliding with pivot box or double action end panel non sl...

Page 4: ...lean and dry location and protect against defacement or damage especially to the edges of panels PREPARATION OF THE OPENING AND SUPPORT STRUCTURE ABOVE Make rough opening width at least 1 2 wider than...

Page 5: ...lable please verify the type of sockets for this order If planning to cut into a post tensioned concrete for bottom door closers pivot boxes and sockets a structural engineer and architect has to be c...

Page 6: ...ews provided See Sheet 4 of the Installation Manual Make sure that the correct angles between segments are maintained and that the transitions between the track segments are perfectly aligned and smoo...

Page 7: ...FORCED TO ENSURE THAT THE UPPER TRACK IS NOT BOWED Upper track segments must be joined such that they are even tight and aligned perfectly Otherwise the running carriages may wear out prematurely whic...

Page 8: ...E HAS TO BE SECURED TO THE SOCKET IN THE PIVOT BOX IN THE FLOOR BEFORE THE SINGLE DOUBLE ACTION SLIDING PANEL CAN FUNCTION PROPERLY OTHERWISE IT WILL NOT BE STABLE AND CAN FALL AND HURT SOMEBODY C GAP...

Page 9: ...hanism is not in the way Make sure the panels are straight and the correct 4 mm gap between panels is maintained Start with the panel furthest away from the parking bay and add blue masking tape under...

Page 10: ...6 52 mm Please check custom product drawing for swing direction inside outside See Sheet 14 and 15 of the Installation Manual Mark this point and if concrete use a diamond core drill bit with 1 1 4 di...

Page 11: ...ip to the edge of the wall Make sure that the full underside of the box rests on a flush and level surface and fix it temporarily into place Then install the receiver box for the top axle by hanging i...

Page 12: ...ed Check if all angles are correct Each leg of the stacking bay track should be equidistant at all points Step F5 Correct any problems before you finish the trimming Do not attach any trimming directl...

Page 13: ...n edge bolt with hand or foot d Automatic Locking when adjacent panels are pulled together and properly aligned the bolt automatically engages 4 Note that there is a carrier at each upper corner of a...

Page 14: ...e head track and engages to the top rail Turn about 8 10 revolutions in a clockwise direction until there is a slight resistance 3 Release the Quick Release Lock on the pivot side to disengage the loc...

Page 15: ...ce Its appearance may be marred by harsh chemicals abuse or neglect Frequency of cleaning depends on exposure and needs For aluminum surfaces generally warm soapy water should be sufficient Stubborn s...

Page 16: ...licable codes and regulations Glass shall meet the current requirements of ASTM C 1306 Standard Specifications for Flat Glass for quality thickness and dimensional tolerances Tempered float glass shal...

Page 17: ...soap and fresh water at least every month and more frequently if necessary After washing the surface should be rinsed thoroughly with clean water and allowed to dry For cleaning do not use abrasive h...

Page 18: ...antial cracking chipping or peeling due to the deterioration of the finish exclusive of mechanical damage 2 chalking in excess of a numerical rating of 8 as per ASTM D 659 or 3 fading or color changes...

Page 19: ...e of the affected product in full satisfaction of its obligations Wood Wood components must be properly finished on all sides promptly after receipt of unit before installation of unit and prior to ex...

Page 20: ...Product selection application storage handling modification or waterproofing Movement of surrounding substrates including deflection of the header of more than or any other stresses on product Instal...

Page 21: ...faces Acts of God falling objects fire accidents external forces or other conditions beyond NanaWall s control Gas fill or retention levels in insulated glass units Field testing of Product Performanc...

Page 22: ...___________________________________ Project Address if different from above _____________________________________________________________ INSTALLATION Installer Name _______________________________ Ad...

Reviews: