Overview
This chapter covers the SC 4812ET BTS site preparation recommended
guidelines.
Installation sites can be classified into one of the three following
categories: Indoor, Rooftop or Outdoor.
All applications will have common requirements and considerations.
Differences between the location site requirements will be covered
throughout the installation section. The following information is meant
to serve as a guideline and can be impacted by site specific
considerations.
Every effort should be made to provide a safe working area
for all installation and service personnel.
WARNING
The mounting surface must be flat. Door closure problems
may occur if the cabinets are not installed on a flat surface.
CAUTION
Care should be taken to ensure that the AC power pedestal
does not interfere with the future addition of expansion or
optional equipment service area.
IMPORTANT
*
Indoor Location
The following items should be considered when choosing an indoor
location for the SC 4812ET BTS:
– A permanent location is more desirable than a temporary one.
– The cabinets should be placed in a location with appropriate
clearance from any obstructions. For minimum clearances see
Chapter 1.
. . . continued on next page