What’s Next and Cleanup
– continued
Apr 2001
V06.03
121
SC
TM
4812ET RF and Power Cabinet Hardware Installation Manual
DRAFT
Table 6-1: Installation Completion Checklist
Status
Notes
Item
No.
11
Power cabinet alarm cable is installed.
12
GPS antenna installed.
13
RGPS antenna cable installed.
14
RF connectors are properly torqued.
15
Power connections are properly torqued.
16
Batteries are installed, and all battery connections
are made with copper–based grease and properly
torqued.
17
Battery shelf retainers are fully seated.
18
Battery heater pads are properly connected.
19
RF cables are labeled the same at both ends.
20
Data cables labeled at both ends.
21
All cables dressed and tied
22
Installation and site specific manuals (log sheet) at
site.
23
Static wrist straps are present.
24
Check all FRUs to verify that they are secure: LPA,
EBA, etc.
25
LPA module cable connector (1/4 turn circular
connector) is fully seated.
26
Visual inspect all door gaskets and verify that front
and rear doors open and close properly
27
Eye bolts are removed and replaced with 5/8 in
bolts (supplied in the installation kit).
28
Install pad locks if desired.
29
Any deficiencies reported to the appropriate people.
30
Site cleaned, swept, and trash removed
31
NOTE
There must be a minimum of 110 Watts power
being dissipated inside the cabinet to prevent
condensation.
6