Site Inspections
DRAFT
SC
300 1X BTS Hardware Installation, ATP, and FRU Procedures
JAN 2002
2-2
Inspection Overview
Inspect the site to verify that the necessary equipment has been properly
installed. Also, as part of the inspection, verify that the equipment is
adequate to support the Motorola equipment. Not all inspections may
apply to every site. The site characteristics determine which inspections
apply.
Installation of ancillary equipment (e.g., power supplies,
terminal blocks, etc.) may be the responsibility of the
installer. Refer questions to your Motorola Program
Manager.
NOTE
Deficiencies
Notify responsible persons of any deficiencies as soon as possible, if the
installer is not responsible for correcting the noted deficiencies.
Deficiencies may need to be corrected before any installation can start.
What to Inspect
The following external items should be inspected and compared against
any related site-specific documentation.
Towers
Antennas
External ground systems
Clearances for units
Mounting Structures
Additionally, for all sites the incoming power should be inspected and
compared against any related site-specific documentation.
Antenna and Tower
Inspections
Documentation
The vendor responsible for supplying the towers should leave the
installation documentation at the site after the tower has been erected.
Review this documentation and compare it with any related site-specific
documents.
Inspection
Inspect the following:
Tower painting
Tower lighting (beacons)
Antenna and transmission line installation
Grounding.
2