Site Preparation Overview
JAN 2002
2-1
SC
300 1X BTS Hardware Installation, ATP, and FRU Procedures
DRAFT
Overview
This chapter provides the procedures and information to verify that the
site is ready to have the equipment installed. It also provides procedures
to ensure the safety of the installation personnel, protect the equipment
from damage, and verify the site layout parameters.
External Installation Versus
Internal Installation
The MicroCell system can be installed outdoors (external) or indoors
(internal). The site preparation depends on the type of installation and
the site characteristics. Most preparations apply to both types (indoor
and outdoor) of installations. It is stated when a preparation applies to
only one type of installation.
All indoor installations must be in a restricted access location.
Verifications and Procedures
The verifications and procedures provided in this chapter are:
External site inspections
Internal site inspections
Preparing site for the arrival of equipment
Site layout verification
Site Manager
The site manager is the person in charge of and responsible for the full
site.
Verifications and Inspections
Verifications typically have the installer check with the site manager that
a condition has been previously checked or procedure previously
performed and meets a stated specification.
Inspections typically have the installer personally checking that a
condition or item meets stated specifications.
2