Starting up for the first time
55
12
Starting up for the first time
After bringing in the boiler, connecting up the hydraulics and power supply, the unit can be started up for the first time.
Note:
The unit must be started up for the first time by an authorised MEco service technician.
Before starting up the pellet boiler, the following settings must be made in the sequence specified below:
1.
Adjust power rating
2.
Settings in the boiler control unit
3.
Output test - test all motors
4.
Settings in heating controller (if installed)
5.
Start the pellet boiler
Use the checklist enclosed to document the start-up procedure.
Property damage
The allowed temperature of the boiler controller is 40 to
122°F.
12.1 Adjusting power rating
On MEco pellet boilers the effective heat exchanger area can be changed within a unti range. This involves opening or
closing the heat exchanger tubes. The power rating of the pellet boiler is adjusted as a result. MEco supplies the pellet
boilers in one type group with the power rating shown below. If the condition as shipped is different from the power rating
on the data plate supplied, then the service technician must adjust the power rating before starting up for the first time.
12.1.1 Installing the turbulators and closure plugs
The heat exchanger in the pellet boiler has between 12 and 36 heat exchanger tubes, depending on the size of the
boiler. Springs are installed inside the heat exchanger tubes to clean the tubes as well as act as turbulators.
Increasing the boiler power rating
1.
Remove the closure plugs from the ends of the heat exchanger tubes.
2.
Insert the turbulators supplied into the heat exchanger tubes.
3.
Hook the turbulators onto the ring of the cleaning system.
Reducing the boiler power rating
1.
Unhook the turbulators from the ring of the cleaning system.
2.
Remove the cleaning springs/turbulators from the heat exchanger tubes.
3.
Close off the heat exchanger tubes using the closure plugs supplied.
PE 3671 USA 2.3
Installation Manual PES 36–56
Summary of Contents for Pellematic PES 12-20
Page 38: ...Connecting up to the power supply 38 Installation Manual PES 36 56 PE 3671 USA 2 3...
Page 46: ...Connecting up to the power supply 46 Installation Manual PES 36 56 PE 3671 USA 2 3...
Page 47: ...Connecting up to the power supply 47 PE 3671 USA 2 3 Installation Manual PES 36 56...
Page 88: ...Appendix 88 Installation Manual PES 36 56 PE 3671 USA 2 3...
Page 92: ...Appendix 92 Installation Manual PES 36 56 PE 3671 USA 2 3...
Page 99: ...Appendix 99 Labeling 105x74 PE 3671 USA 2 3 Installation Manual PES 36 56...
Page 100: ......