A. Pull vacuum to 1000 microns. Break the vacuum
with dry nitrogen and sweep the system. Pressurize
to a minimum of .35 bar.
B. Change the vacuum pump oil.
C. Pull vacuum to 500 microns. Break the vacuum
with dry nitrogen and sweep the system. Pressurize
to a minimum of .35 bar.
D. Change the vacuum pump oil.
E. Pull vacuum to 500 microns. Run the vacuum pump
for 1 hour additional hour.
Charge the system with the proper refrigerant to the
nameplate charge.
Operate the ice machine for one hour. Then, check
the pressure drop across the suction line filter-drier.
F. If the pressure drop is less than .14 bar, the filter-
drier should be adequate for complete cleanup.
G. If the pressure drop exceeds .14 bar, change the
suction line filter-drier and the liquid line drier.
Repeat until the pressure drop is acceptable.
Operate the ice machine for 48-72 hours. Replace
the suction line and liquid line drier if necessary.
Important
Dry nitrogen is recommended for this procedure.
This will prevent CFC release.
Summary of Contents for UG018A
Page 2: ......
Page 6: ...This Page Intentionally Left Blank ...
Page 12: ... 2 This Page Intentionally Left Blank ...
Page 20: ...10 Evaporator Spray Nozzles Toggle Switch Spray Bar Ice Chute ...
Page 36: ...26 dip switch Decrease Cube Size Factory Default Setting Increase Cube Size test button ...
Page 38: ...28 ...
Page 80: ...70 This Page Intentionally Left Blank ...
Page 128: ... 118 This Page Intentionally Left Blank ...
Page 135: ... 125 ...