INSTALLATION
Wall mounted gas boilers work with natural gas, LPG and Propan; hence the
installation of these items must be carried out by only authorised delaers.
IMPORTANT ISSUES
•
Pipings must be cleaned before the installation of the unit.
•
The gas connection of the unit must be done properly and controlled for any
leakages.
•
Hermetic boilers operate on closed burning chamber principle therefore the
unit supplies the air from outside for burning then exhausts the burned gases
o the environment.Hence the gas exhaust flue must be installed in connection
with the outer environment.
•
Gas flues must not be put in closed areas where there is no air circulation.
•
Wall mounted boiler must be installed vertically on a firm wall.
•
The unit must not be installed in connection with dirty and oily flue where the
kitchen appliances are connected to.
•
The below space dimensions must be maintained around the unit in order to
provide the immediate service intervention during a failure or maintainence.
•
Installation accesories provided along with the boiler( wall plug,screw and
hooks) must be used during the installation.
•
The proper installation checked by a spirit level is necessary for the healthy
operation of the boiler.
SPACES TO BE LEFT DURING INSTALLATION
When there is a failure or a maintainence, in order to reach out to the inner
components of the boiler, at least the below spaces must be maintained.The
suggested spaces are minimum dimensions and can be increased
accordingly.
9