WATERFLOOD TO THE SYSTEM AND FOLLOWING WATER PRESSURE
Installation water pressure can be displayed digitally on LCD Screen. To display
the pressure, place P1 Button as TEST, P2 Button as SUMMER on control panel
(page 7). Water pressure will be displayed as bar.
In first waterflooding air from radiators must be taken. Please do the firstflooding
in reference to these steps:
1- Open all purgers in central boiler installation and in radiators.
Attention:
Rotate the water evacuation holes and place a pot under every purger
in order to prevent damages of water.
2- Open the filling valve (page 11) which is placed underside of boiler and start
filling water into the system.
3- Close all the pugers when blister-free water comes from purgers.
4- Continue to flood until the system pressure comes up to 1,5 Bar and turn off
the filling valve.
Attention:
It is recommended to make first flooding at least 2 people.While one
person is controlling the radiators and closing the pugors, other one can control
the pressure by standing over the boiler and close the filling valve it is needed.
It is necessary to add water by opening filling valve in closed circuit system after
running of boiler. Radiators must be checked if there is air in them or not.
PUTTING INTO SERVICE
Boiler must be put into service by only Tecnical Services in order to run the boiler
efficient and safe , also for the validation of guarantee conditions.
A)PRE- CONTROLS BEFORE PUTTING INTO SERVICE
1. The gas type and its pressure must be controlles.
2. Automatic purgor fuse on the circulation pump must be loosened.
3. The pressure inside the system must control from the manometer. The
pressure must be around 1,5 Bar.
4. In order to dispose the air from all of the system , take out the screw in front
of the pump.By this way, whether the pump mill is congested or not can be
controlled and any air that is congested can be discharged.
5. Dispose the air from the purgers on the radiator.
6. Discharge the air in the hot water system by turning on hot water tap.
7. Check the installation of hermetic flue kit.
8. Check whether all valves in the system are turned on.
12