2.0 Installation
2.1 Guidelines for Foundation
To ensure that the equipment is solidly bolted to the ground under all operation
conditions, a foundation with the following dimensions shall be provided:
Depth of foundation:
at least 3ft (frost-depth)
Base area of foundation: 19” x 23 ½”
The base of the foundation is 4” wider towards the vehicle passage side, than in other
section of the foundation (see Fig. S0225).
Fig. S0225
View of the foundation
1 Anchor
bolts
(4x)
2 Empty conduit for induction loop lead wire, dia. ½”
3 Conduit for power cables, dia. 1”
4 Conduit for control cables, dia. ½”
5 Concrete foundation
Conduit pipes (with different diameters for low and high voltage cables as per
Electrical code) must be installed to run the mains supply cable, the control cables
and the induction loop lead wires.
A reinforcing steel cage is absolutely essential for the stability of the foundation (see
Fig. S0102).
Abb. S0102
Steel reinforcement for
The concrete foundation
5 x
∅
3/8”/17 ½” x 17 ½” St III
3 x
∅
½”/ 29” x 16” St III
1
2
3
4
5
31
1/2
S0225
Foundation at
frost-line depth 3’
Concrete
foundation
PC 250
1 Conduit 1/2” for loop lead wires
1 Conduit 3/4” for power supply
must be extended and connected
to junction box
1 Conduit 1/2”” for control