Lucent Technologies Victory Class Batteries WP-93936
Issue 1 May 2000
Installation 6 - 17
Installing Standard and Seismic Racks, continued
Seismic Rack
Assembly
10. Install all back restraint rail(s) and cover(s). See Figure 6-8.
11. Position front restraint rail and cover temporarily next to front
support rail prior to installing cells.
Leveling and
Securing Rack
Assembly
12. Check that the rack is level and square.
13. Torque down all bolts. First torque the cross brace bolts to 55-65
ft.-lbs, then torque the rail to frame bolts to 15-20 ft.-lbs. Torque
anchor bolts to manufacturer's recommended value.
Figure 6-8: Initial Step for Seismic Rack
With Detail of Frame and Restraint Rail(s) (Reverse View)
Frame
Restraint Rail
and Cover
Back Restraint
Rail and Cover
3/8-16 Hex Bolt
Lock Washer and
Serrated Nut