6 - 16 Installation
Issue 1 May 2000
Installing Standard and Seismic Racks, continued
Installing Support
Rail(s)
5. Place support rail(s) in location using supplied 3/8" bolt, washer,
and serrated strut nut; finger tighten. See Figure 6-7.
6. Align support rails with “A” dimension from rack assembly
drawing.
7. Install rail covers.
8. An internal/external “star” washer is used in place of lock washer
on bottom tier or step, for grounding connection. The optional
third rail should be installed at this time.
9. If installing a Standard rack, proceed to “Leveling and Securing
Rack Assembly.” If installing a Seismic rack, perform Steps 10
and 11.”
Figure 6-7: Support Rail Installation With Detail of Frame
and Support Rail Connection
3/8-16 Hex Bolt
Washer (Lock or Star)
and Serrated Nut
Support Rail
and Cover
Support Rail
and Cover
Frame