Lucent Technologies Victory Class Batteries WP-93936
6 - 6 Installation
Issue 1 May 2000
Rack Installation Guidelines, continued
Back to Back
Orientation
Where two rows of racks are required, two rack assemblies may be
installed in parallel back to back.
Locate back to back frames relative to each other as shown, so that the
rear cross brace attachment holes align for the two adjoining frames.
All braces must be installed, as described previously, except that a
single bolt may be used to connect the front and rear frames and
respective cross braces. Use 3/16" spacers and/or washers to fill gaps
between adjacent frames. See Figure 6-3.
End to End
Orientation
Where a continuous rack string is required, two racks may be installed
adjacent in length.
End to end rack assemblies are installed as two individual, stand-alone
rack assemblies as shown in Figure 6-4. When installing standard racks,
the minimum clearance between racks is 0". When installing Seismic
racks the two racks must be spaced apart so that the minimum distance
between the ends of the support rails is 5".
Figure 6-3: Back to Back Rack Assembly
Front of Rack A
Front of Rack B
Back of Racks A and B
Figure 6-4: End to End Rack Assembly