Commissioning
Leuze electronic
VR 2300
23
TNT
35/7-2
4
V
7
Commissioning
7.1
Measures to be performed prior to the first commissioning
©
Before commissioning, familiarise yourself with the operation and configuration of the
device(s)!
©
Before switching on, recheck all connections and ensure that they have been properly
made.
7.2
Function Test
"Power On" test
After connecting the operating voltage, the VR 2300 carries out an automatic "Power On"
function test. Subsequently, the red LED (in the standard setting) lights up in the optics
window of the VR 2300.
Interface
Proper function of the interface can be tested easiest in service operation using the interface
with the VisionREADER Setup Tool programming software and a notebook computer. For
order numbers, see table 5.1 on page 13.
Problems
Should problems occur during device commissioning, refer first to chapter 8.2. Should a
problem persist after checking all electrical connections and settings on the devices and
host, please contact a Leuze service office near you (see the back page of this operating
manual).
7.3
Setting the Parameters
You have now commissioned the VR. Usually, you will have to configure it before you can
use it. Using the parameter options made available by the VR, you may configure the VR to
suit your individual area of application. For instructions regarding the various setting options
refer to chapter 9 or to the online help of the VisionREADER Setup Tool.
In order to operate the VR, it is typically sufficient to set code type and code length in accord-
ance with the codes that are to be read. However, depending on the application, you will
additionally configure the switching inputs and outputs according to your requirements.
To understand what is happening during the parameter setting, the following chapter 7.3.1
briefly explains the various parameter sets.
The setting of the parameter sets then takes place in the operating mode "service", which is
described in chapter 7.3.2.