66
Step 8
Install a temporary working platform
made from sturdy planks.
Ensure that you are standing safely and
have the platform handed up to you.
Place the platform on the temporary
working plat-form to reduce the risk of
accidents.
NOTE:
To erect and dismantle the scaffold, you
must install temporary working platforms.
These plat-forms are made from planks
and must be removed after completion of
the installation or disassembly. According
to DIN EN 12811-1, the planks used for
tempo-rary work-ing platforms must have
a width of minimum 20 cm and a thick-
ness of minimum 4 cm. They must extend
by at least 50 cm on both sides of the
scaffold.
Step 9
Attach the platform to the top rungs of
the vertical frames, using the openings
provided. Secure it by tightening the
previously mounted securing kits.
Summary of Contents for ProTec XS
Page 2: ...2 DE FaltGer st ProTec XS 3 GB Folding scaffold ProTec XS 45...
Page 29: ...29 Die Abbildung zeigt das fertig montierte Ger st mit einer Arbeitsh he von 5 80 m...
Page 53: ...53 Identification The type plate above is attached to the vertical frames of the ProTec system...
Page 70: ...70 Fully mounted scaffold with a working height of 5 80 m...
Page 86: ...86 Notice...
Page 87: ...87 Notice...