51
Safety distance 1 m
for rated voltages up to 1000 V
Safety distance 3 m
for rated voltages from 1 kV to 110 kV
Safety distance 4 m
for rated voltages from 110 kV to 220 kV
Safety distance 5 m
for rated voltages from 200 kV to 380 kV
If these safety distances cannot be maintained, contact the operator of the overhead
line to arrange for a shut down.
Also ensure that the system is protected against inadvertent switching on while work is
being carried out.
4. Installation of scaffold
4.1 General
The scaffold may only be installed, after all parts of section 2 on the product and the
safety instructions in section 3 have been read in full. At least two workers are required
to erect the scaffold. Before starting the erection work, ensure that all necessary com-
ponent parts and tools are available on the site of installation and that the parts of the
scaffold are not defec-tive. Use only original component parts that meet the specifica-
tions of the manufacturer.
NOTE ON THE USE OF THE INSTALLATION INSTRUCTIONS
The installation manual describes the various installation options of the ProTec system.
Read the entire installation manual before erecting the scaffolding and consider the dif-
ferent installation options.
Depending on the height above ground of the top accessible board, the scaffold might
have to be stabilised with ballasts or outriggers. For more detailed instructions, see the
last chapter of this installation and user manual.
Summary of Contents for ProTec XS
Page 2: ...2 DE FaltGer st ProTec XS 3 GB Folding scaffold ProTec XS 45...
Page 29: ...29 Die Abbildung zeigt das fertig montierte Ger st mit einer Arbeitsh he von 5 80 m...
Page 53: ...53 Identification The type plate above is attached to the vertical frames of the ProTec system...
Page 70: ...70 Fully mounted scaffold with a working height of 5 80 m...
Page 86: ...86 Notice...
Page 87: ...87 Notice...