Section 3 Installation Instructions
3.8 Operation Tests
Hazardous voltage.
Can cause severe injury or death.
Operate the generator set only when
all guards and electrical enclosures
are in place.
Moving parts.
WARNING
1. Check the items in the Prestart Checklist in the
generator set Operation Manual, including the oil
and coolant levels.
2. Move the generator set master switch to the RUN
position to start the generator set.
3. Use a digital voltmeter (DVM) to check the output
voltage from the generator set.
If voltage
adjustments are required, refer to Section 5.5 for
instructions to use the ADC 2100 voltage
adjustment menu.
4. Perform voltage checks as described in the ATS
Operation and Installation manual. Close the main
circuit breaker on the main distribution panel when
instructed to connect power in the test procedure.
5. Test the system operation as described in the ATS
Operation and Installation manual.
6. Set the exerciser on the transfer switch. Refer to
the instructions in the ATS Operation and
Installation manual.
7. Verify that the generator set master switch is in the
AUTO position.
8. Verify that all guards and enclosures are in place.
Summary of Contents for 15REYG
Page 1: ...Commercial Generator Sets Models 15REYG 30REYG TP 6727 10 11c Installation...
Page 16: ...TP 6727 10 11 16 Section 1 General Notes...
Page 44: ...TP 6727 10 11 44 Section 5 Controller Notes...
Page 48: ...TP 6727 10 11 48 Section 6 Generator Reconnection Notes...
Page 64: ...TP 6727 10 11 64 Notes...
Page 65: ...TP 6727 10 11 65 Notes...
Page 66: ...TP 6727 10 11 66 Notes...
Page 67: ......