Storage
If the Server is not installed immediately, please store the Server vertically together
with its packing box in a dry room with the direction of sunshine according to the mark on
the packing box, to avoid dust and high temperature environment.
2.2
Installation Notices
This chapter gives a general description of the requirements of the Server for the site
selection and wiring layout of the Server. Due to the peculiarity of each site, this
chapter does not give a detailed description of installation steps, only provides the
instructional general installation steps and methods to the installation personnel, who will
conduct the installation based on the specific conditions of the installation site. Please note:
The installation at the site must be done by qualified engineers authorized by the
Company for the installation;
During the electrical connection, the Server should be grounded first and all the
switches should be cut off before the installation of the Server is completed.
The Server should be installed by qualified engineers according to the descriptions in
this chapter in combination with the local standards. This manual will be provided with
detailed mechanical and electrical installation information when there is no related
delivery information of other devices.
When connecting the battery, the voltage at the battery terminal will be more than 360
VDC which possesses the risk of fatal danger. Please take off rings, bracelets, watches,
and other metal articles. The tools with insulated handle(s) must be used. Please wear
rubber gloves. If there is leakage of the battery electrolyte or the battery is broken,
please replace the battery and put it in the container with the resistance to sulfate
corrosion and dispose it according to the local regulations. If your skin comes into
contact with the battery the electrolyte, please flush it with water immediately and seek
medical assistance.
2.3
Unpacking Inspection
When unpacking the case of the Server, please make the inspections as follows:
1. Take a visual inspection to make sure that there is no deformation, damage and
dislocation or other damage in transportation on the internal or external surface of the
Server and the battery. If there is any damage, do not install or use the system, please
notify Kilowatt Labs, Inc. immediately.
2. Check the technical data sheet of the product to confirm whether it is the right
equipment. The technical data sheet of the Server is located on the label on the
internal side of the front door, with the model, capacity and main parameters of the
Server indicated on the label.
2.4
Determination of Mounting Positions
Please pay attention to the following requirements for the selection of the Server’s
installation space:
1.
This Server must be installed in a clean and dry room (the environment temperature
within 0 ~ 40
℃
, the relative humidity of 5% ~ 90%, and the optimal operating
temperature of 25
℃
). If the room temperature is 40
℃
, the indoor exhaust fan should