background image

ITABAR-Sensor  Type 

IBFD

 Operating 

Manual 

almost identical to the type IBFD-65. The only 
difference is the end support (with a weldolet for 
type IBFD-66 ; see Fig. 15), which permits higher 
stream velocities in the pipe. 

Except for the installation of the sensor end support, 
the installation steps are identical to those for type 
IBFD-65. 

Installation of the closed sensor end support: 

1.  Install the mounting flange as already described 

under chapter 5.6. points 1 to 6. 

2.  Take a cord and tie one end around the existing 

weld stud. Wrap the other end of the cord around 
the pipe so that it forms a loop around the pipe. 
Mark the half-way point of the pipe 
circumference on the pipe. 

3.  Now drill a second hole of 60 mm diameter into 

the pipe. 

4.  Insert the ITABAR sensor through the mounting 

flange and check correct alignment. Put the 
weldolet (item A, fig. 15) on the pipe. 
 
 
 

 

 

 

 

 

 

Fig. 15 

5.  Tack the weldolet (item A) with 4mm clearance 

onto the pipe. 

6.  Remove the sensor. 

7.  Finish welding of weldolet (item A). 

8.  Insert the ITABAR sensor through the mounting 

flange and install the ring (item B, fig. 15). If it´s 
not possible, because the tolerance of welding 
are to much, so you are able to machine the ring 
(clearence into the weldolet -0,2mm). 

9.  Now you can weld the endcap (item C, fig. 15) 

onto the weldolet (item A). 

 

 

6. Insulation 

 

It is important for proper operation of the ITABAR 
steam sensor that the phase change from vapour to 
liquid take place only in the therefore specially 
designed condensation vessels and not in the head 
of the sensor. 
Therefore, the entire sensor head and all other parts 
up to the condensation vessels must be insulated 
with a suitable material. 
Before being insulated, all piping connections 

should be checked for leaks and the instrument 
connection for the differential pressure have to be 
marked ( + and - ) to prevent confusion. 
Finally, the ITABAR TAG-plate must hang outside 
the insulation for later identification of the flow 
station. 
 

ATTENTION! 

Do not insulate the condensation vessels, valves and 
the lines to the differential pressure transmitter! 
The media there have to be in liquid state. 
 

7. 

Installation of valve block and 

 the 

p-transmitter 

7.1. Valve 

block 

For steam measurement a 3-valve instrument 
manifold is recommended. The valves of a 3-valve 
manifold has the following functions: 

•  Valve C and D shut-off to transmitter, 
•  Valve E Bypass valve (transmitter zero), 
 

If a 5-valve instrument manifold will be used the 
valve has additional function: 

•  valve F and G for drains 

See Fig. 13a and b 
 

7.2. 

p-Transmitter 

For steam measurements, the differential pressure 
transmitter should always be installed below the 
ITABAR sensor in order to avoid the occurrence of 
air bubbles in the instrument connections (see 
Fig. 

13a and b). Take care to mount the dp-

transmitter exactly horizontal, otherwise a small 
difference to alignment is followed by a zero point 
error. 
We recommend you to install the differential 
pressure lines close together (connect hi and lo line 
heat conducting) to maintain equal temperature. 
 
 
 
 
 
 
 

11 

Summary of Contents for ITABAR-Flow-Sensor IBFD

Page 1: ...Installation Notes 3 5 Installation of the ITABAR Sensor 7 6 Insulation 11 8 Measurement Start Up 13 9 Preventive Maintenance 13 10 Trouble shooting sensors with condensate pots 13 INTRA AUTOMATION G...

Page 2: ...you can not neglect friction The dynamic energy will not be transmitted to the differential transmitter without faults You will not get correct measuring results 1 Product Description We congratulate...

Page 3: ...hickness of pipe For horizontal and vertical pipe run the condensation vessels have to be arranged in the same horizontal plain Compare Fig 3b and 4b Fig 1 Horizontal pipe run Fig 2 Vertical pipe run...

Page 4: ...izontal Pipe Arrangement Always install the ITABAR steam sensor horizontally with the instrument connections condensation vessels along a horizontal line Fig 4a and 4b Fig 4a Installation for horizont...

Page 5: ...re subject to wear The sensor is not affected by being slightly out of alignment The influence on the accuracy of the measurements is negligible as long as the limits indicated in Figures 5 6 and 7 ar...

Page 6: ...asuring stretch by conducting a comparison measurement The measurement guarantees that the differential pressure corresponds to the true flow velocity thereby assuring the specified accuracy The follo...

Page 7: ...otential energy This is eliminated for ITABAR Flow Sensors Observe the general installation instructions It is particularly important to make sure that the distance from the gasket surface to the pipe...

Page 8: ...sensor Fig 10 5 Tack the sensor end support with 2 mm clearance onto the pipe 6 Remove the sensor 7 Finish welding of mounting flange and end support can be made 8 Perform the installation of the sen...

Page 9: ...etween this two parts see Fig 12 ATTENTION Please take care on the H dimension in case you did not co ordinate the weld preparation of the pipe system with our work To make sure that sensor matches yo...

Page 10: ...mounting flange again this is important for the exact position of the condensation vessels 5 Now the ITABAR sensor can be installed into the pipe Place the included gasket on the gasket surface of th...

Page 11: ...liquid take place only in the therefore specially designed condensation vessels and not in the head of the sensor Therefore the entire sensor head and all other parts up to the condensation vessels m...

Page 12: ...ITABAR Sensor Type IBFD Operating Manual Sensor with condensate pots K5 6 7 Fig 13a Sensor with condensate pots K1 Fig 13b 12...

Page 13: ...pressure indication Correction Check whether all instrument valves to the p transmitter are opened The valve E must be closed only for zero Check the alignment of the sensor with the pipe The arrow o...

Reviews: