The installation of the types IBFD-65 correspond to 
the type IBFD-20. The only different is, that the 
mounting stud is designed with a weldolet. 

1.  Drill a hole of 60 mm diameter into the pipe. 

2.  Tack the mounting flange onto the pipe leaving a 

clearance of 4 mm. The bolt holes of the flange 
must be at 22,5° angles to the pipe axis (see Fig. 
13). Check the alignment of the mounting 
flange. 

 

Fig. 13 
 
3.  Observe the H-dimension during the welding of 

the mounting flange (see also Fig. 14). 

 

 

 

 

 

 

 

 

 
Fig. 14 
 
4. Check the alignment of the mounting flange 

again - this is important for the exact position of 
the condensation vessels. 

5.  Now the ITABAR sensor can be installed into 

the pipe. Place the included gasket on the gasket 
surface of the flange. Insert the sensor into the 
welded stud and make sure that the arrow on the 
sensor flange points in the flow direction. 
Tighten the bolts and nuts. 

6.  Now check the alignment of the condensation 

vessel. The condensation vessel have to be 
perfectly mounted along a horizontal line. 

 

Check the alignment! 

 

For correction of alignment slightly release stud 
bolts on the mounting flange. For correct align-

ment tighten stud bolts with required torque 
according table 1. 

5.7. 

Installation of Type IBFD-66 

The design of the ITABAR sensor IBFD-66 is  

22,5°

 

10 

Summary of Contents for ITABAR-Flow-Sensor IBFD

Page 1: ...Installation Notes 3 5 Installation of the ITABAR Sensor 7 6 Insulation 11 8 Measurement Start Up 13 9 Preventive Maintenance 13 10 Trouble shooting sensors with condensate pots 13 INTRA AUTOMATION G...

Page 2: ...you can not neglect friction The dynamic energy will not be transmitted to the differential transmitter without faults You will not get correct measuring results 1 Product Description We congratulate...

Page 3: ...hickness of pipe For horizontal and vertical pipe run the condensation vessels have to be arranged in the same horizontal plain Compare Fig 3b and 4b Fig 1 Horizontal pipe run Fig 2 Vertical pipe run...

Page 4: ...izontal Pipe Arrangement Always install the ITABAR steam sensor horizontally with the instrument connections condensation vessels along a horizontal line Fig 4a and 4b Fig 4a Installation for horizont...

Page 5: ...re subject to wear The sensor is not affected by being slightly out of alignment The influence on the accuracy of the measurements is negligible as long as the limits indicated in Figures 5 6 and 7 ar...

Page 6: ...asuring stretch by conducting a comparison measurement The measurement guarantees that the differential pressure corresponds to the true flow velocity thereby assuring the specified accuracy The follo...

Page 7: ...otential energy This is eliminated for ITABAR Flow Sensors Observe the general installation instructions It is particularly important to make sure that the distance from the gasket surface to the pipe...

Page 8: ...sensor Fig 10 5 Tack the sensor end support with 2 mm clearance onto the pipe 6 Remove the sensor 7 Finish welding of mounting flange and end support can be made 8 Perform the installation of the sen...

Page 9: ...etween this two parts see Fig 12 ATTENTION Please take care on the H dimension in case you did not co ordinate the weld preparation of the pipe system with our work To make sure that sensor matches yo...

Page 10: ...mounting flange again this is important for the exact position of the condensation vessels 5 Now the ITABAR sensor can be installed into the pipe Place the included gasket on the gasket surface of th...

Page 11: ...liquid take place only in the therefore specially designed condensation vessels and not in the head of the sensor Therefore the entire sensor head and all other parts up to the condensation vessels m...

Page 12: ...ITABAR Sensor Type IBFD Operating Manual Sensor with condensate pots K5 6 7 Fig 13a Sensor with condensate pots K1 Fig 13b 12...

Page 13: ...pressure indication Correction Check whether all instrument valves to the p transmitter are opened The valve E must be closed only for zero Check the alignment of the sensor with the pipe The arrow o...

Reviews: