8
Mar 2016
MSC-18K
2. Seat and fasten the batteries
on the column base, secure to
base using provided metal
straps.
3. Connect the power cables to
batteries. ( Fig. 5)
4. Install the battery covers back on lift.
Fig. 5 Battery Installation
NOTE: Ensure to correctly connect terminals: Red/Pos. = (+), Black/Neg. = (-)
STEP 4. Cable Reel Installation
1. Take out the cable reels from the carton.
2. Insert the holding frame into the base on the upper cover (Figs. 6a&b)
Fig. 6a Fig. 6b Fig. 6c
3. Pull up and pull down the upper and down lock button, the reel can turn aside.
(Fig. 6c)
4.
Fix the reel on the base by the screw. (Fig 6d)
Fig. 6d Fig. 6e
5.
Put the cable plug into the socket. (Fig 6e)
6.
Repeat the above steps for the other three columns
STEP 5. Pre-charging the batteries
If the newly installed batteries are not charged, please charge them before operation.
Charging steps refers to chapter 5.1 on page 23
Summary of Contents for MSC-18K-B
Page 5: ...4 Mar 2016 MSC 18K 1 2 DIMENSIONS mm inch Fig 1 Mobile Column Lift Dimensions...
Page 34: ...33 Mar 2016 MSC 18K MSC 18K B EXPLODED VIEWS PARTS LISTS MSC 18K Column Assembly...
Page 39: ...38 Mar 2016 MSC 18K MSC 18K Control Panel Assembly...
Page 41: ...40 Mar 2016 MSC 18K MSC 18K Power Unit Assembly...