STS-6000K-H1 Smart Transformer Station (Vietnam,
Duc Long Gai Lai)
Installation Guide
8 Verifying the Installation and Cable Connections
Issue 02 (2020-02-21)
Copyright © Huawei Technologies Co., Ltd.
63
8
Verifying the Installation and Cable
Connections
No.
Acceptance criteria
1
All onsite components are installed correctly and securely.
2
All switches are OFF.
3
All cables are connected correctly and securely.
4
All screws are tightened.
5
Unused cable holes are covered with waterproof caps.
6
The cable holes in use are sealed.
7
The installation space is proper, and the installation environment is clean
and tidy.
8
All doors of the STS are closed and properly locked.