FusionModule1000A20 Prefabricated All-in-One Data
Center
Installation Guide
6 Installing Devices Inside the Pre-fab. Module
Issue 02 (2020-01-15)
Copyright © Huawei Technologies Co., Ltd.
67
Context
The ASD power box and batteries inside the pre-fab. module have been installed before
delivery. You only need to connect the reserved cables to the batteries onsite.
Preparations
Tools: Phillips screwdriver
Materials: none
Skill requirement: common technician
Procedure
Step 1
Open the power box using a key.
Step 2
Remove the protective foam from the battery and check whether the battery is intact or leaks.
If the battery is damaged or leaks, contact Huawei technical support to replace the battery.
Step 3
Connect the reserved battery cable.
Distinguish the positive and negative battery terminals when connecting a battery cable.
Figure 6-35
ASD battery wiring diagram