FusionModule1000A20 Prefabricated All-in-One Data
Center
Installation Guide
4 Installing Pre-fab. Modules
Issue 02 (2020-01-15)
Copyright © Huawei Technologies Co., Ltd.
27
Context
Ensure that the crane and steel ropes can bear the load weight.
Table 4-3
Hoisting specifications
Weight
Steel
Rope
Length
Steel Rope
Quantity
Dimensions (H x W x D)
Net weight: <
6000 kg
> 6.5 m
4 PCS
2896 mm x 2438 mm x 6058 mm
Hoisting Precautions
Stage
Precautions
Before hoisting
Ensure that the crane and steel ropes provide the required bearing
capacity.
Ensure that the twistlocks in container bases are in correct positions.
Ensure that the steel ropes are securely connected.
During hoisting
Do not allow any unauthorized people to enter the hazardous areas
and never stand under the crane arm during hoisting.
Ensure that the crane is properly located and avoid long-distance
hoisting.
Keep the pre-fab. module stable and horizontal during hoisting, and
ensure that the diagonal gradient of the pre-fab. module is within 5
degrees.
Lift and land a pre-fab. module slowly to prevent shock to
equipment inside it.
Remove the ropes after ensuring that the pre-fab. module is placed
evenly on the four bases.
Preparations
Tools: crane, torque wrench, steel hoisting rope, level
Materials: pre-fab. module to be hoisted, spacer
Documents: none
Skill requirement: skilled technician, common technician, crane driver
Procedure
Step 1
Adjust the pre-fab. module in the installation direction, connect the steel hoisting ropes, and
hoist the pre-fab. module onto the bases.